    Satellite Group Lianyungang Petrochemical's 1.25 million tons/year ethylene three plants successfully tested for the first time

    • Last Update: 2022-08-23
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    It was reported on April 17 that when the company fully resumed work and production, there was good news from the final assembly workshop: Satellite Group Lianyungang Petrochemical 3.
    2 million tons/year comprehensive utilization project of young hydrocarbons - 1.
    25 million tons/year ethylene three machines all successfully completed the no-load test run tasks, shaft vibration, bearing pad temperature, lubricating oil temperature and other indicators meet the standard requirements


    .


    Lianyungang Petrochemical's 3.
    2 million tons/young hydrocarbon comprehensive utilization project is the first million-grade pure ethane-to-ethylene chemical project in China.
    Compared with the traditional naphtha-to-ethylene and methanol-to-olefin processes, ethane cracking to ethylene has the advantage of cracking gas.
    The components are relatively simple, the ethylene recovery rate is high, and the follow-up market potential is huge


    .


    At the beginning of the project, the leaders of the company attached great importance to it.
    General Manager Ye Zhong personally led the team to the headquarters of Satellite Petrochemical Company and had a comprehensive communication with the leaders of Satellite Petrochemical Company on the project situation; after that, the marketing team and the technical team were highly coordinated, and after several rounds of business, Through technical exchange and negotiation, the company successfully stood out from the fierce competition of other well-known manufacturers, and won the bid for all 6 sets of steam turbines of binary refrigeration compressors, propylene refrigeration compressors and cracked gas compressors in this project


    .


    However, due to the delay in supply of bearing manufacturers, and the delay in resumption of work by the company due to the epidemic, the commissioning and delivery of the unit were also forced to be postponed.
    During this period, in order to minimize the losses caused by the delay, the assembly workshop and The research institute actively implements the corporate core values ​​of customer first, unites as one, convened on-site review and coordination meetings for many times, checked and checked the unit data many times, and demonstrated a variety of feasible backup solutions


    .


    Looking back at the ethylene units in recent years, from Zhanjiang 800,000 to Sinochem Quanzhou 1 million ethylene three units, from Wanhua 1 million tons of ethylene to Dalian Hengli with an annual output of 1.
    5 million tons of ethylene cracking gas units, the second room of the steam turbine adheres to the enterprising spirit , The spirit of innovation, step by step, gradually set foot on the cutting edge of the world


    .


    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.