Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
On July 9, local time, at the coordination meeting for the overall completion and commissioning of the Northwest Crude Oil Pipeline Transformation Project of China National Petroleum International Pipeline Co.
, Ltd.
in Almaty, Kazakhstan, the Kazakhstan shareholder representative Alinov stated that the construction of the transformation project was completed.
The "West-East Oil Delivery" within Kazakhstan will be realized, and more crude oil will be exported to China, which is of far-reaching significance to the energy cooperation between the two countries
.
Prior to this, on July 1, the Oman Pumping Station of the Northwest Crude Oil Pipeline Reverse Transmission and Reconstruction Project held a completion and acceptance ceremony
.
This indicates that the Northwest Crude Oil Pipeline, after more than two years of construction, has officially reached the 6 million tons/year reverse oil delivery capacity planned by the project.
In November 2018, the first phase of the reverse transmission and transformation project of the Northwestern Kazakhstan crude oil pipeline was launched.
After the preliminary construction, it was put into operation on June 17, 2020, reaching a reverse transmission capacity of 3 million tons/year; the second phase of the project started in December 2019 Construction, of which the newly-built Oman pumping station is a key project to ensure that the reverse oil delivery capacity reaches 6 million tons/year
.
The completion and acceptance of the Oman pumping station as scheduled, marking the completion of all key main projects of the second phase of the reverse transmission and transformation project, and will lay a solid foundation for the complete completion and commissioning of the reverse transmission and transformation project within the year
In order to achieve the construction goals on schedule, the Northwest Crude Oil Pipeline Joint Venture of China National Petroleum International Pipeline Company adheres to the guidance of "anti-epidemic production with both hands, health and benefits" as a guide, and forms a community of destiny with contractors, overcomes many difficulties, and makes every effort to accelerate the speed of Oman pumping station Construction progress
.
The company has fully absorbed the latest international experience in epidemic prevention and control, updated the prevention and control measures manual and plan, and encrypted the frequency of supervision and inspection to ensure the strict implementation of on-site epidemic measures, and the project construction has always been orderly and steadily advanced
Project construction implements full-cycle upgrade management
.
As the owner, the Northwest Crude Oil Pipeline Joint Venture Company has fully and deeply involved in the design, procurement, construction site management and other specific aspects of project implementation, helping contractors to solve practical difficulties such as epidemic prevention and control and shortage of funds in accordance with laws and regulations
In addition, the shareholders of China and Kazakhstan have closely communicated and coordinated, accelerated the approval process, and resolved key and difficult issues facing the project in a timely manner