    Progress of CNPC International Pipeline Project in Kazakhstan

    • Last Update: 2021-08-05
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    On July 9, local time, at the coordination meeting for the overall completion and commissioning of the Northwest Crude Oil Pipeline Transformation Project of China National Petroleum International Pipeline Co.
    , Ltd.
    in Almaty, Kazakhstan, the Kazakhstan shareholder representative Alinov stated that the construction of the transformation project was completed.
    The "West-East Oil Delivery" within Kazakhstan will be realized, and more crude oil will be exported to China, which is of far-reaching significance to the energy cooperation between the two countries
    .

    Prior to this, on July 1, the Oman Pumping Station of the Northwest Crude Oil Pipeline Reverse Transmission and Reconstruction Project held a completion and acceptance ceremony
    .


    This indicates that the Northwest Crude Oil Pipeline, after more than two years of construction, has officially reached the 6 million tons/year reverse oil delivery capacity planned by the project.


    In November 2018, the first phase of the reverse transmission and transformation project of the Northwestern Kazakhstan crude oil pipeline was launched.
    After the preliminary construction, it was put into operation on June 17, 2020, reaching a reverse transmission capacity of 3 million tons/year; the second phase of the project started in December 2019 Construction, of which the newly-built Oman pumping station is a key project to ensure that the reverse oil delivery capacity reaches 6 million tons/year
    .


    The completion and acceptance of the Oman pumping station as scheduled, marking the completion of all key main projects of the second phase of the reverse transmission and transformation project, and will lay a solid foundation for the complete completion and commissioning of the reverse transmission and transformation project within the year


    In order to achieve the construction goals on schedule, the Northwest Crude Oil Pipeline Joint Venture of China National Petroleum International Pipeline Company adheres to the guidance of "anti-epidemic production with both hands, health and benefits" as a guide, and forms a community of destiny with contractors, overcomes many difficulties, and makes every effort to accelerate the speed of Oman pumping station Construction progress
    .


    The company has fully absorbed the latest international experience in epidemic prevention and control, updated the prevention and control measures manual and plan, and encrypted the frequency of supervision and inspection to ensure the strict implementation of on-site epidemic measures, and the project construction has always been orderly and steadily advanced


    Project construction implements full-cycle upgrade management
    .


    As the owner, the Northwest Crude Oil Pipeline Joint Venture Company has fully and deeply involved in the design, procurement, construction site management and other specific aspects of project implementation, helping contractors to solve practical difficulties such as epidemic prevention and control and shortage of funds in accordance with laws and regulations


    In addition, the shareholders of China and Kazakhstan have closely communicated and coordinated, accelerated the approval process, and resolved key and difficult issues facing the project in a timely manner




    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.