    PowerChina's Sujiatun Wind Farm Project achieved the target of putting 20 wind turbines into operation ahead of schedule

    • Last Update: 2022-11-21
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    On May 19, the 18# and 19# wind turbines of Qinglong Sujiatun Wind Farm, independently invested and constructed by PowerChina Guiyang Institute, were successfully connected to the grid for power generation, and 20 wind turbines were put into operation more than ten days earlier than planned
    .

    Sujiatun Wind Farm is located in Angu Township and Jichang Township, Qinglong County, Qianxian Buyi and Miao Autonomous Prefecture, Guizhou Province, and the wind farm adopts 21 direct-drive wind turbines with a single capacity of 2MW, with a total installed capacity of 42MW
    .

    Since the construction of Sujiatun Wind Farm began, Guiyang Institute has fully promoted the construction of the wind farm with the strong support of the local government and all participants, and since the first wind turbine was put into operation on January 1, 2016, it has achieved the important goal
    of putting all other wind turbines into operation in less than 5 months, except for the 11# wind turbine affected by the goaf area.

    On May 19, the 18# and 19# wind turbines of Qinglong Sujiatun Wind Farm, independently invested and constructed by PowerChina Guiyang Institute, were successfully connected to the grid for power generation, and 20 wind turbines were put into operation more than ten days earlier than planned
    .

    Wind power

    Sujiatun Wind Farm is located in Angu Township and Jichang Township, Qinglong County, Qianxian Buyi and Miao Autonomous Prefecture, Guizhou Province, and the wind farm adopts 21 direct-drive wind turbines with a single capacity of 2MW, with a total installed capacity of 42MW
    .

    Since the construction of Sujiatun Wind Farm began, Guiyang Institute has fully promoted the construction of the wind farm with the strong support of the local government and all participants, and since the first wind turbine was put into operation on January 1, 2016, it has achieved the important goal
    of putting all other wind turbines into operation in less than 5 months, except for the 11# wind turbine affected by the goaf area.

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.