Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
On December 29th, the 2# 100,000 cubic meter storage tank dome gas jacking project of Wuhu Yangtze River LNG inland river receiving (transshipment) station undertaken by Petrochemical Sijian Storage and Transportation Company was successfully completed
.
2# Storage tank As the first storage tank to complete the gas jacking in the project project, the civil construction has been completed and is ready to move to the next stage of internal tank installation
.
Wuhu Yangtze River LNG inland river receiving (transshipment) station project is the first inland LNG storage tank in the Yangtze River Basin and a key project in Anhui Province, and Petrochemical Sijian Storage and Transportation Company has always attached great importance to
this project.
At the end of the year, the employees involved in the construction of the engineering project department faced the adverse factors such as severe winter cold and epidemic, actively organized the establishment of party members and youth shock teams, strengthened project safety management, improved welding efficiency, ensured welding quality, increased modular construction efforts, deepened the dome sheet preset depth and modular hoisting, special inspection of sales items before jacking, etc.
, air pressure ceiling is a crucial step
in the tank capping work.
In the process of air jacking, the method of decentralized balance system is adopted to synchronously monitor the air volume pressure, rising speed, dome levelness, and jacking height data to ensure that the lifting process is always in a high standard controlled state, with the joint efforts of all the construction personnel, the steel dome weighing more than 570 tons and a diameter of about 70 meters rose smoothly to a height of nearly 40 meters, accurately reached the design position, and the tank top pressure ring perfectly fitted, lasting 83 minutes, high quality, high efficiency successfully completed the air jacking
.
It is also the 11th storage tank perfectly jacked by Petrochemical Sijian Storage and Transportation Company in 2022!