    Petrochemical No. 4 Construction undertook the construction of Wuhu Yangtze River LNG storage tank, and achieved successful dome gas jacking

    • Last Update: 2023-02-02
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    On December 29th, the 2# 100,000 cubic meter storage tank dome gas jacking project of Wuhu Yangtze River LNG inland river receiving (transshipment) station undertaken by Petrochemical Sijian Storage and Transportation Company was successfully completed
    .
    2# Storage tank As the first storage tank to complete the gas jacking in the project project, the civil construction has been completed and is ready to move to the next stage of internal tank installation
    .

    Wuhu Yangtze River LNG inland river receiving (transshipment) station project is the first inland LNG storage tank in the Yangtze River Basin and a key project in Anhui Province, and Petrochemical Sijian Storage and Transportation Company has always attached great importance to
    this project.
    At the end of the year, the employees involved in the construction of the engineering project department faced the adverse factors such as severe winter cold and epidemic, actively organized the establishment of party members and youth shock teams, strengthened project safety management, improved welding efficiency, ensured welding quality, increased modular construction efforts, deepened the dome sheet preset depth and modular hoisting, special inspection of sales items before jacking, etc.
    , air pressure ceiling is a crucial step
    in the tank capping work.

    In the process of air jacking, the method of decentralized balance system is adopted to synchronously monitor the air volume pressure, rising speed, dome levelness, and jacking height data to ensure that the lifting process is always in a high standard controlled state, with the joint efforts of all the construction personnel, the steel dome weighing more than 570 tons and a diameter of about 70 meters rose smoothly to a height of nearly 40 meters, accurately reached the design position, and the tank top pressure ring perfectly fitted, lasting 83 minutes, high quality, high efficiency successfully completed the air jacking
    .
    It is also the 11th storage tank perfectly jacked by Petrochemical Sijian Storage and Transportation Company in 2022!

                                                       

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.