    Overcoming difficulties, the project construction does not stop - the construction record of the IPCI-UO project in Kazakhstan

    • Last Update: 2022-10-10
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    The Kazakh Petrochemical Integration (IPCI) project is one of the key projects under construction in Kazakhstan, and it is also the largest chemical project in the country's infrastructure construction.


    Strengthen epidemic prevention and control

    Give full play to the leading role of party building

    In 2020, the new crown pneumonia epidemic broke out.


    During the construction process, the project department increased investment in epidemic prevention and control, and distributed protective clothing, isolation masks, anti-virus masks and preventive traditional Chinese medicine to all on-site personnel


    During the extraordinary period of the epidemic and the most critical stage of project construction, Communist Party members wrote hymns on the construction site with practical actions


    Create construction conditions

    Advance construction progress in an orderly manner

    In order to ensure the orderly progress of the construction progress, the project department refined the division of labor of each department, reversed the construction period plan, fought with pictures on the wall, and dispatched at any time in case of major problems


    In the concrete construction stage, in order to create favorable conditions for night work, the project duty personnel coordinate in advance the night construction work related matters, such as night work tickets, concrete pump trucks, tank trucks and other vehicles entering and leaving the factory permit


      After the construction of the project has fully entered the secondary structure construction stage, in order to ensure the completion of the subsequent construction period goals, the project department once again uses the node control method to ensure the construction progress management, make the construction plan more detailed, and conduct timely assessments of the progress every week.


      Strengthen quality management

      Resolutely Fulfill Safety Commitments

      In order to improve the overall construction quality of the project and improve the level of project performance, the project department holds a special quality meeting every week to summarize and analyze the quality risks existing in the process, formulate quality risk pre-control measures, formulate quality control points, and check on-site quality at designated points.


      In terms of safety management, the project department actively promotes the management of the real-name information platform for laborers, focusing on labor management and safety production and environmental protection, so as to ensure their rights and interests


      At present, all majors of the Kazakhstan IPCI-UO project are in full swing to carry out the final clearing work, and the project construction has reached the final sprint stage.




    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.