    Maoming Petrochemical's first set of steam pressure matching device was put into operation

    • Last Update: 2021-08-28
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    China Petrochemical News Network reported at the end of July that Maoming Petrochemical’s first steam pressure matcher was installed and commissioned, and it was officially put into use on the No.
    3 steam turbine of the CFB boiler plant in the refining area
    .

    At the beginning of this year, after the 2.
    6 million tons/year slurry bed unit was put into use, low-pressure steam was produced by by-products, which led to a reduction in the amount of low-pressure steam supplied to the entire plant from the CFB boiler in the refinery area.
    In summer, more than 20 tons of low-pressure steam were vented per hour.
    , Resulting in energy waste
    .


    The professional technical backbone of the thermoelectric division took the lead in tackling the problem, and proposed to add a steam pressure matcher to the boiler installation to increase the amount of surplus low-pressure steam, avoid low-pressure steam venting, reduce high and reduce steam waste, increase steam turbine power generation, and further reduce CFB boiler installations Energy consumption, to achieve the effect of energy saving and consumption reduction


    In July of this year, the No.
    3 steam turbine in the refining area was shut down for maintenance.
    The Thermal Power Division seized this favorable opportunity to organize and implement the installation of a new steam pressure matcher
    .


    The newly-added steam pressure matcher is installed in the vacancy on the south side of the No.


    In order to ensure the smooth completion of the project, the technology, equipment and safety professions of the first power plant are closely watching the scene.
    After more than 20 days of intense construction, the equipment installation and commissioning tasks have been completed with high quality
    .


    The equipment was successfully put into production at the end of July .


      At present, the first set of steam pressure matching device is operating normally, and can use high and low pressure steam to mix into medium pressure steam about 12 tons per hour
    .


    It is understood that they will continue to add one steam pressure matcher to the No.


    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.