Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
From May 24, Maoming Petrochemical’s port branch will use the tanker’s arrival window to organize the overhaul of the offshore single-point mooring floating terminal oil terminal, mainly the system No.
In order to ensure the safety and efficiency of the overhaul, Maoming Petrochemical Port Division’s marine operations team earnestly implemented the Group’s General Manager No.
During the operation, the branch leaders are in command, the professional departments are on-site supervised, the workshop leadership team and the mooring chief conduct on-site command at the offshore construction site, and the party member commando team is set up to strengthen the construction supervision around the clock.
Beginning in mid-May, the sea team has arranged a dedicated person to follow the single-point sea area semi-monthly forecast, weekly forecast, three-day forecast and 24-hour forecast provided by the South China Sea Forecast Center.
From the evening of the 28th, in the face of the deteriorating sea conditions, the sea team adjusted its operation plan.
On June 2, the port sea team completed the inspection and inspection of the 300,000-ton-class single-point mooring and the watertightness test of the pipeline system, and successfully completed the single-point overhaul, with the conditions for commissioning, 8 days ahead of schedule.