Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
On the occasion of the company's full resumption of work and production, good news came from the assembly workshop: Satellite Group Lianyungang Petrochemical 3.
2 million tons/year comprehensive utilization project of young hydrocarbons - 1.
25 million tons/year ethylene three machines have successfully completed the no-load test task, shaft vibration, bearing Various indicators such as tile temperature and lubricating oil temperature meet the standard requirements
.
Lianyungang Petrochemical's 3.
2 million tons/young hydrocarbon comprehensive utilization project is the first million-grade pure ethane-to-ethylene chemical project in China.
Compared with the traditional naphtha-to-ethylene and methanol-to-olefin processes, ethane cracking to ethylene has the advantage of cracking gas.
The components are relatively simple, the ethylene recovery rate is high, and the follow-up market potential is huge
.
At the beginning of the project, the leaders of the company attached great importance to it.
General Manager Ye Zhong personally led the team to the headquarters of Satellite Petrochemical Company and had a comprehensive communication with the leaders of Satellite Petrochemical Company on the project situation; after that, the marketing team and the technical team were highly coordinated, and after several rounds of business, Through technical exchange and negotiation, the company successfully stood out from the fierce competition of other well-known manufacturers, and won the bid for all 6 sets of steam turbines of binary refrigeration compressors, propylene refrigeration compressors and cracked gas compressors in this project
.
However, due to the delay in supply of bearing manufacturers, and the delay in resumption of work by the company due to the epidemic, the commissioning and delivery of the unit were also forced to be postponed.
During this period, in order to minimize the losses caused by the delay, the assembly workshop and The research institute actively implements the corporate core values of customer first, unites as one, convened on-site review and coordination meetings for many times, checked and checked the unit data many times, and demonstrated a variety of feasible backup solutions
.
The hard work pays off, the T6D04 ethylene three-unit cracking gas unit successfully completed the test run at 19:30 on January 15, 2020.
The maximum vibration of the unit is 11μm, and the bearing temperature is up to 75°C.
The data indicators are excellent, and the user's satisfaction has been obtained.
Unanimously praised; the T6D00 ethylene three-unit binary refrigeration unit successfully completed the commissioning after the company fully resumed work.
The unit has a maximum vibration of 9 μm and a maximum bearing temperature of 75 °C.
So far, the satellite group Lianyungang Petrochemical 3.
2 million tons/young hydrocarbon comprehensive utilization project— —The 1.
25 million tons/year ethylene three machines have all successfully completed the no-load commissioning task, and all your efforts have paid off
.
Looking back at the ethylene units in recent years, from Zhanjiang 800,000 to Sinochem Quanzhou 1 million ethylene three units, from Wanhua 1 million tons of ethylene to Dalian Hengli with an annual output of 1.
5 million tons of ethylene cracking gas units, the second room of the steam turbine adheres to the enterprising spirit , The spirit of innovation, step by step, gradually set foot on the cutting edge of the world
.