Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
Kenya has reportedly announced the upcoming Lake Turkana wind power project
.
The project, which will start at the end of this month, almost doubled the overall project cost after more than 18 months of delays, to 28 billion shillings, up from 15 billion shillings
.
Before President Uhuru Kenyatta commissioned the plant to production, Energy Cabinet Minister Charles Keter conducted a final simulation
of the power plant's project.
He promised that electricity bills would be reduced
once the wind farm was officially put into operation.
He explained, "Due to the increase in fuel costs due to the new fuel VAT, the completion of this wind power project has helped us to reduce the use of fossil fuels
such as diesel.
”
:/, please indicate the source for reprinting)
Kenya has reportedly announced the upcoming Lake Turkana wind power project
.
The project, which will start at the end of this month, almost doubled the overall project cost after more than 18 months of delays, to 28 billion shillings, up from 15 billion shillings
.
Before President Uhuru Kenyatta commissioned the plant to production, Energy Cabinet Minister Charles Keter conducted a final simulation
of the power plant's project.
He promised that electricity bills would be reduced
once the wind farm was officially put into operation.
He explained, "Due to the increase in fuel costs due to the new fuel VAT, the completion of this wind power project has helped us to reduce the use of fossil fuels
such as diesel.
”
:/, please indicate the source for reprinting)
/