    Jihua (Jieyang) Acrylonitrile Project Department completed stand-alone test work

    • Last Update: 2022-10-21
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    On June 19, the acrylonitrile project of Jihua (Jieyang) successfully completed the single-type work of 164 motors, and completed the node target 3 days ahead of schedule
    .

    Since the on-site general substation was successfully powered on May 30, in order to ensure the success of the motor test, the project department started the first time, and actively communicated with all parties about possible problems during the test run according to the detailed test plan prepared in advance.

    .
    Before commissioning, organize relevant professionals to carry out withstand voltage tests on on-site cables and motors; repeatedly confirm wiring and grounding conditions; The opening and closing simulation test is carried out on the operation column; the torque tightening test is carried out on the busbar.
    .
    .
    Every step is strictly in accordance with the relevant safety and quality management regulations, one inspection and one inspection step by step, and the single test work of the motor is steadily promoted

    .

    The meticulous and rigorous preparatory work in the early stage provided a solid guarantee for the successful operation of the motor.
    On June 4, under the joint witness of the owner, the supervisor, the general contractor and the manufacturer, the first high-voltage motor was successfully operated

    .

    The project department overcame the unfavorable factors brought by the "Dragon Boat Water" for more than ten consecutive days, and insisted on "no work without light rain, and dry when heavy rain stopped".
    After 16 days of unremitting efforts, the single work of 164 motors was successfully completed, 3 days ahead of schedule High-quality completion of node goals has been highly recognized by general contractors, supervisors, and owners

    .

     Although the follow-up tasks are still very heavy, the project department will continue to carry forward the "iron army" spirit of the Sixth Construction, meticulously organize, work hard, and forge ahead, work hard for the goal of the project, and contribute to Ji Petrochemical's "building the world's most advanced ABS device" Six construction forces, with excellent results to welcome the party's 20th National Congress victory
    .

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.