    Jieyang project construction is in full swing!

    • Last Update: 2022-09-23
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    At present, the progress of PetroChina's Guangdong Petrochemical refining and chemical integration project: the first combined atmospheric and vacuum unit and the second combined delayed coking unit have ushered in the mechanical completion, the steel structure of the 19-kilometer pipe gallery has been completed, and the ethylene unit cracking furnace furnace tube has been fully welded


    In 2022, PetroChina's Guangdong Petrochemical refining and chemical integration and Jilin Petrochemical ABS projects will be completed and put into production


    The world-class green petrochemical industry base is accelerating its rise

    The world-class green petrochemical industry base is accelerating its rise

    On February 8, the 8 cracking furnaces of the ethylene unit of the PetroChina Guangdong Petrochemical Refining and Chemical Integration Project completed all the welding work, marking the completion of the construction of the cracking furnace project, one of the three main lines of the ethylene unit


    Guangdong Petrochemical's ethylene plant has a total of 6 double-chamber liquid furnaces and 2 double-chamber gas furnaces, each with a scale of 200,000 tons per year, and the single-scale liquid furnace is the largest in China


    During the Spring Festival, the steel structure of the pipe gallery involved in the ignition of the power area of ​​the Guangdong Petrochemical Project was fully connected


    The project construction progress provided by Guangdong Petrochemical Company shows that as of February 8, the entire project has completed 94.


    Since the beginning of this year, the construction site of Guangdong petrochemical project has blossomed in many places, and good news has been reported frequently:

    On January 23, Guangdong Petrochemical Refining and Chemical Integration Project 1 completed construction nodes such as the three towers, main process pipelines and the main body of the heating furnace in conjunction with the atmospheric and vacuum unit, and successfully achieved the mechanical completion;

    On January 28, the 3 million tons/year delayed coking unit of the second combined unit achieved mechanical completion, marking that the construction of the second combined project will be transferred to the stage of trial run preparation


    According to the construction plan of Guangdong Petrochemical Company this year, the next will focus on key nodes such as the ignition of the power center, the delivery of the main equipment, the entry of crude oil, and the commissioning of the main equipment to promote the high-quality start of production of the entire project this year


    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.