    Home > Chemicals Industry > Rubber Plastic News > Involving Wanhua, SK, Donghua New Materials, etc.!

    Involving Wanhua, SK, Donghua New Materials, etc.!

    • Last Update: 2022-08-28
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    [1] Wanhua integrated bisphenol A with an annual output of 480,000 tons

    [1] Wanhua integrated bisphenol A with an annual output of 480,000 tons

    The underground foundation is completed, the underground pipeline is basically completed, and the installation of the steel structure is 20% completed


    .


    On July 23, 2020, Wanhua Chemical held a groundbreaking ceremony for the bisphenol A integrated project with an annual output of 480,000 tons


    .


    The project includes a 530,000-ton/year cumene production line, a 650,000-ton/year phenol acetone production line, a 480,000-ton/year bisphenol A production line, as well as public works and auxiliary facilities


    .


    【2】Wanhua Chengda Chemical

    【2】Wanhua Chengda Chemical

    The basic construction is basically completed, and the main construction and the installation of the steel structure frame are being promoted, and about 55% are completed


    .


    【3】Wanhua Citral

    【3】Wanhua Citral

    The project approval and safety assessment have been completed, the special section on safety design has been approved, the environmental impact assessment has passed the review and is awaiting approval, the main building drawing review has been completed, and the construction drawing design is in progress, about 55% completed


    .


    【4】Linde Gas Phase III

    【4】Linde Gas Phase III

    The main equipment in the cold box has been hoisted, and the pipeline installation is 70% complete


    .


    【5】SK High-end Fine Chemicals

    【5】SK High-end Fine Chemicals

    The environmental pre-assessment expert review has passed


    .


    【6】Donghua New Materials

    【6】Donghua New Materials

    40% of the R&D office building has been completed; the basic construction of the multi-functional special resin workshop is underway; the design and review of the construction drawings of the canteen, locker room, and doorman have been completed; the construction drawing design of public works and storage and transportation devices is in progress


    .


    【7】BGI Chemicals

    【7】BGI Chemicals

    1# Auxiliary workshop foundation construction and main construction are completed, and masonry construction begins
    .

    【8】Merui New Materials

    【8】Merui New Materials

    The safety and environmental impact assessment has been completed, the drawing review is in the second round of response, the bidding for the construction of the civil structure has been completed, and the contract for the dynamic compaction pile foundation has been signed
    .

    【9】Haihong old man paint

    【9】Haihong old man paint

    The civil works such as the workshop, warehouse, office, etc.
    have been basically completed, and finishing work such as greening is being carried out

    .
    The main production equipment, tank farm, supporting fire protection system, waste gas treatment, sewage treatment and other equipment are in place, and the remaining pipeline electrical instruments are currently being completed

    .

    【10】Jinqiao Unocal New Material

    【10】Jinqiao Unocal New Material

    The main construction is completed
    .
    Masonry construction is 80% complete, and decoration construction is 40% complete

    .

    [11] Jiumu Chemistry

    [11] Jiumu Chemistry

    The foundation construction is 85% completed, and the A01 workshop has completed the first floor formwork and steel reinforcement construction; the A02 workshop has completed the foundation construction, and the A03 workshop has completed 20% of the foundation construction; other auxiliary workshops and supporting facilities are in the process of applying for construction permits
    .

    【12】Baoneng Logistics Center Project

    【12】Baoneng Logistics Center Project

    The decoration construction is in progress, 50% completed, and the construction units for the doors, windows and glass curtain walls of the office building have been determined
    .

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.