    The construction of the foundations of the three towers of the PDH plant has been completed

    The construction of the foundations of the three towers of the PDH plant has been completed

    On November 30, the construction of the three tower foundations of the 700,000-ton/year propane dehydrogenation (PDH) unit of the first bid section of the Jiangsu Sailbon Petrochemical Co.


    The three towers are a depropanizer, a deethane stripper, and a propylene-propane separation tower


    Since the start of construction, the project department has strived to complete the civil construction with high standards.


    In the next step, the project department will further improve the preparatory work before the entry of large-scale equipment, and lay a solid foundation for subsequent equipment hoisting


    The first tower of acrylonitrile plant was successfully hoisted into place

    On December 02, the first light organics stripper of the AN3 unit of the second bid section of the Sierbang Phase II propane industry chain project supervised by Luoyang Petrochemical Engineering Construction Group Co.


    The light organics stripping tower is 26.


    With the joint efforts of all parties involved in the construction, overcoming the influence of many unfavorable factors such as environment and transportation, after one and a half hours of hoisting operation, the first light unit of the AN3 unit in the second bid section of the second phase of the Propane Industrial Chain Project of Sailbond was successfully completed.


    On November 30, the construction of the three tower foundations of the 700,000-ton/year propane dehydrogenation (PDH) unit of the first bid section of the Jiangsu Sailbon Petrochemical Co.


    On November 30, the construction of the three tower foundations of the 700,000-ton/year propane dehydrogenation (PDH) unit of the first bid section of the Jiangsu Sailbon Petrochemical Co.


    The three towers are a depropanizer, a deethane stripper, and a propylene-propane separation tower


    The three towers are a depropanizer, a deethane stripper, and a propylene-propane separation tower


    Since the start of construction, the project department has strived to complete the civil construction with high standards.


    Since the start of construction, the project department has strived to complete the civil construction with high standards.


    In the next step, the project department will further improve the preparatory work before the entry of large-scale equipment, and lay a solid foundation for subsequent equipment hoisting


    The first tower of acrylonitrile plant was successfully hoisted into place

    In the next step, the project department will further improve the preparatory work before the entry of large-scale equipment, and lay a solid foundation for subsequent equipment hoisting


    The first tower of acrylonitrile plant was successfully hoisted into place

    The first tower of acrylonitrile plant was successfully hoisted into place

    On December 02, the first light organics stripper of the AN3 unit of the second bid section of the Sierbang Phase II propane industry chain project supervised by Luoyang Petrochemical Engineering Construction Group Co.


    The light organics stripping tower is 26.
    9 meters high, 1.
    7 meters in diameter, and weighs about 16 tons for a single piece of equipment.
    The construction unit has formulated a reasonable hoisting plan according to the actual situation on site.
    The tower adopts the double-machine lifting method, and the main crane adopts a 200-ton truck crane.
    25-ton truck crane was selected as the auxiliary crane.
    In order to ensure that the equipment is hoisted in place at one time, the project supervision department carefully reviewed the hoisting construction plan, re-measured parameters such as foundation strength, position, elevation, reference line, etc.
    , and reviewed the qualifications of special operators and cranes and slings.
    , the quality certification documents of the spreader, check the foundation bearing capacity report

    .
    Before hoisting, the supervisors shall check and accept the laying and leveling of the horns, and confirm the hoisting weather, working conditions, and safety of the locks to ensure that the hoisting is foolproof

    .

    With the joint efforts of all parties involved in the construction, overcoming the influence of many unfavorable factors such as environment and transportation, after one and a half hours of hoisting operation, the first light unit of the AN3 unit in the second bid section of the second phase of the Propane Industrial Chain Project of Sailbond was successfully completed.
    The hoisting of the organic stripper has successfully completed the node task of the project construction.
    The serious and responsible work attitude of the project supervision department has been highly praised by the construction unit

    .

    On December 02, the first light organics stripper of the AN3 unit of the second bid section of the Sierbang Phase II propane industry chain project supervised by Luoyang Petrochemical Engineering Construction Group Co.
    , Ltd.
    was successfully hoisted into place

    .

    The light organics stripping tower is 26.
    9 meters high, 1.
    7 meters in diameter, and weighs about 16 tons for a single piece of equipment.
    The construction unit has formulated a reasonable hoisting plan according to the actual situation on site.
    The tower adopts the double-machine lifting method, and the main crane adopts a 200-ton truck crane.
    25-ton truck crane was selected as the auxiliary crane.
    In order to ensure that the equipment is hoisted in place at one time, the project supervision department carefully reviewed the hoisting construction plan, re-measured parameters such as foundation strength, position, elevation, reference line, etc.
    , and reviewed the qualifications of special operators and cranes and slings.
    , the quality certification documents of the spreader, check the foundation bearing capacity report

    .
    Before hoisting, the supervisors shall check and accept the laying and leveling of the horns, and confirm the hoisting weather, working conditions, and safety of the locks to ensure that the hoisting is foolproof

    .

    With the joint efforts of all parties involved in the construction, overcoming the influence of many unfavorable factors such as environment and transportation, after one and a half hours of hoisting operation, the first light unit of the AN3 unit in the second bid section of the second phase of the Propane Industrial Chain Project of Sailbond was successfully completed.
    The hoisting of the organic stripper has successfully completed the node task of the project construction.
    The serious and responsible work attitude of the project supervision department has been highly praised by the construction unit

    .

    On December 02, the first light organics stripper of the AN3 unit of the second bid section of the Sierbang Phase II propane industry chain project supervised by Luoyang Petrochemical Engineering Construction Group Co.
    , Ltd.
    was successfully hoisted into place

    .

    On December 02, the first light organics stripper of the AN3 unit of the second bid section of the Sierbang Phase II propane industry chain project supervised by Luoyang Petrochemical Engineering Construction Group Co.
    , Ltd.
    was successfully hoisted into place

    .

    The light organics stripping tower is 26.
    9 meters high, 1.
    7 meters in diameter, and weighs about 16 tons for a single piece of equipment.
    The construction unit has formulated a reasonable hoisting plan according to the actual situation on site.
    The tower adopts the double-machine lifting method, and the main crane adopts a 200-ton truck crane.
    25-ton truck crane was selected as the auxiliary crane.
    In order to ensure that the equipment is hoisted in place at one time, the project supervision department carefully reviewed the hoisting construction plan, re-measured parameters such as foundation strength, position, elevation, reference line, etc.
    , and reviewed the qualifications of special operators and cranes and slings.
    , the quality certification documents of the spreader, check the foundation bearing capacity report

    .
    Before hoisting, the supervisors shall check and accept the laying and leveling of the horns, and confirm the hoisting weather, working conditions, and safety of the locks to ensure that the hoisting is foolproof

    .

    The light organics stripping tower is 26.
    9 meters high, 1.
    7 meters in diameter, and weighs about 16 tons for a single piece of equipment.
    The construction unit has formulated a reasonable hoisting plan according to the actual situation on site.
    The tower adopts the double-machine lifting method, and the main crane adopts a 200-ton truck crane.
    25-ton truck crane was selected as the auxiliary crane.
    In order to ensure that the equipment is hoisted in place at one time, the project supervision department carefully reviewed the hoisting construction plan, re-measured parameters such as foundation strength, position, elevation, reference line, etc.
    , and reviewed the qualifications of special operators and cranes and slings.
    , the quality certification documents of the spreader, check the foundation bearing capacity report

    .
    Before hoisting, the supervisors shall check and accept the laying and leveling of the horns, and confirm the hoisting weather, working conditions, and safety of the locks to ensure that the hoisting is foolproof

    .

    With the joint efforts of all parties involved in the construction, overcoming the influence of many unfavorable factors such as environment and transportation, after one and a half hours of hoisting operation, the first light unit of the AN3 unit in the second bid section of the second phase of the Propane Industrial Chain Project of Sailbond was successfully completed.
    The hoisting of the organic stripper has successfully completed the node task of the project construction.
    The serious and responsible work attitude of the project supervision department has been highly praised by the construction unit

    .

    With the joint efforts of all parties involved in the construction, overcoming the influence of many unfavorable factors such as environment and transportation, after one and a half hours of hoisting operation, the first light unit of the AN3 unit in the second bid section of the second phase of the Propane Industrial Chain Project of Sailbond was successfully completed.
    The hoisting of the organic stripper has successfully completed the node task of the project construction.
    The serious and responsible work attitude of the project supervision department has been highly praised by the construction unit

    .

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.