Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
At 13:00 on October 19th, Harbin Petrochemical Company built a newly built 500,000-ton/year gas fractionation unit whose propylene water content fell below 20ppm, and put into use a propylene refining system, marking the successful start-up of the 500,000-ton/year gas fractionation unit.
At 13:00 on October 19th, Harbin Petrochemical Company built a newly built 500,000-ton/year gas fractionation unit whose propylene water content fell below 20ppm, and put into use a propylene refining system, marking the successful start-up of the 500,000-ton/year gas fractionation unit.
This device is a key project for the transformation and upgrading of Harbin Petrochemical's refining and chemical industry, and one of the top 100 construction projects in Heilongjiang Province.
The construction of the project started in October 2019 and will be completed in August 2020.
Since the completion of the project, in order to ensure a successful start-up, Harbin Petrochemical Company's production, equipment, safety, engineering and other professional backbones have adhered to the site and actively coordinated the work in charge.
As the main force, the first joint workshop has prepared plans in advance and detailed tasks.
, Responsibility goes to people, identify the risks of key steps, and do a good job in safety management.
Installation staff work overtime to carry out preliminary work such as "three checks and four determinations", construction blind removal, steam purging, air-tightness and nitrogen replacement, highlighting the inspection of the installation safety facilities, and promptly handles the problems found and sells them.
In the process of feeding and starting, the keyboard is carefully operated internally, and the external operation is carefully inspected.
The start-up operation card is strictly implemented, steady and steady, step-by-step confirmation, and the whole process is controlled to achieve zero accidents, zero pollution, and zero leakage during the start-up process.