    Haiyang Nuclear Power Unit 1 was successfully connected to the grid for the first time, and the unit was in good condition

    • Last Update: 2022-11-26
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    At 9:50 on August 17, Haiyang Nuclear Power Unit 1 was successfully connected to the grid for the first time, and all technical indicators met the design requirements and the unit was in good condition
    .

    Haiyang Nuclear Power Unit 1 began its first charging on June 21, 2018, the reactor reached critical for the first time on August 8, and successfully used nuclear steam to successfully flush the turbine to the rated speed for the first time on August 14, and successfully completed the tests
    before the turbine generator was connected to the grid.
    After being connected to the grid, Unit 1 will enter the load-bearing trial operation state and continue to carry out the load-bearing related test projects to prepare
    for commercial transportation.

    Shandong Nuclear Power has always adhered to the principle of "safety first, quality first", strictly abides by national laws and regulations, complies with power grid dispatching instructions, and meticulously operates in accordance with technical procedures, ensuring the success
    of the first grid connection.

    At 9:50 on August 17, Haiyang Nuclear Power Unit 1 was successfully connected to the grid for the first time, and all technical indicators met the design requirements and the unit was in good condition
    .

    nuclear power

    Haiyang Nuclear Power Unit 1 began its first charging on June 21, 2018, the reactor reached critical for the first time on August 8, and successfully used nuclear steam to successfully flush the turbine to the rated speed for the first time on August 14, and successfully completed the tests
    before the turbine generator was connected to the grid.
    After being connected to the grid, Unit 1 will enter the load-bearing trial operation state and continue to carry out the load-bearing related test projects to prepare
    for commercial transportation.

    Shandong Nuclear Power has always adhered to the principle of "safety first, quality first", strictly abides by national laws and regulations, complies with power grid dispatching instructions, and meticulously operates in accordance with technical procedures, ensuring the success
    of the first grid connection.

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.