Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
A few days ago, the Fourth Construction Company held the kick-off meeting of the Hainan Refining and Chemical 1 million tons/year ethylene and oil refining reconstruction and expansion project, making overall planning and early preparations to ensure the smooth start of the project construction
.
The 1 million tons/year ethylene and oil refining reconstruction and expansion project department of Hainan Refining and Chemical Company of the Fourth Construction Company is managed according to the weak matrix model of one project department + three sub-project departments
.
The 1 million tons/year ethylene and oil refining reconstruction and expansion project department of Hainan Refining and Chemical Company of the Fourth Construction Company is managed according to the weak matrix model of one project department + three sub-project departments
.
Fourth Construction Company has undertaken four construction tasks in Hainan Refinery, namely 1 million tons/year ethylene unit, 2.
6 million tons/year hydrocracking unit, PX aromatics transformation, and LPG low temperature tank.
The total contract value is estimated to be 1.
2 billion.
Yuan Renminbi
.
The 2.
6 million ton/year hydrocracking and aromatics reformation unit started on December 16, 2020, the 1 million tons/year ethylene unit started on January 16, 2021, and the hydrocracking and aromatics reforming unit is planned for March 30, 2022 The ethylene plant is scheduled to be handed over on June 30, 2022, and the material delivery was successful on September 30
.
The leaders of the Fourth Construction Company, the second-level units, and the personnel of the project department inspected the site, the office camp, and the prefabricated factory, and conducted docking discussions, including the determination of the project type, the planning and layout of temporary construction, the division of economic responsibilities for large-scale machinery, material procurement, equipment allocation management, Overall contract situation, contract risk warning, follow-up market development, resource assurance, resource allocation, talent training, safety and quality target control and measures, environmental protection laws and regulations, green construction site creation, technical construction plans, high-tech, intelligent software applications and needs The problems that can be solved by project coordination, etc.
, can be solved on the spot, and the problems that cannot be solved on the spot have a timetable, and the responsibility is assigned to the head, which lays the foundation for the high start of the project construction
.
The leaders of the Fourth Construction Company, the second-level units, and the personnel of the project department inspected the site, the office camp, and the prefabricated factory, and conducted docking discussions, including the determination of the project type, the planning and layout of temporary construction, the division of economic responsibilities for large-scale machinery, material procurement, equipment allocation management, Overall contract situation, contract risk warning, follow-up market development, resource assurance, resource allocation, talent training, safety and quality target control and measures, environmental protection laws and regulations, green construction site creation, technical construction plans, high-tech, intelligent software applications and needs The problems that can be solved by project coordination, etc.
, can be solved on the spot, and the problems that cannot be solved on the spot have a timetable, and the responsibility is assigned to the head, which lays the foundation for the high start of the project construction
.