    Hainan Refinery's 1 million tons/year ethylene and refining expansion project kick-off meeting was held

    • Last Update: 2022-08-27
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    A few days ago, the Fourth Construction Company held the kick-off meeting of the Hainan Refining and Chemical 1 million tons/year ethylene and oil refining reconstruction and expansion project, making overall planning and early preparations to ensure the smooth start of the project construction


    .


    The 1 million tons/year ethylene and oil refining reconstruction and expansion project department of Hainan Refining and Chemical Company of the Fourth Construction Company is managed according to the weak matrix model of one project department + three sub-project departments


    .


    The 1 million tons/year ethylene and oil refining reconstruction and expansion project department of Hainan Refining and Chemical Company of the Fourth Construction Company is managed according to the weak matrix model of one project department + three sub-project departments
    .


    Fourth Construction Company has undertaken four construction tasks in Hainan Refinery, namely 1 million tons/year ethylene unit, 2.
    6 million tons/year hydrocracking unit, PX aromatics transformation, and LPG low temperature tank.
    The total contract value is estimated to be 1.
    2 billion.
    Yuan Renminbi


    .


    The 2.
    6 million ton/year hydrocracking and aromatics reformation unit started on December 16, 2020, the 1 million tons/year ethylene unit started on January 16, 2021, and the hydrocracking and aromatics reforming unit is planned for March 30, 2022 The ethylene plant is scheduled to be handed over on June 30, 2022, and the material delivery was successful on September 30


    .


    The leaders of the Fourth Construction Company, the second-level units, and the personnel of the project department inspected the site, the office camp, and the prefabricated factory, and conducted docking discussions, including the determination of the project type, the planning and layout of temporary construction, the division of economic responsibilities for large-scale machinery, material procurement, equipment allocation management, Overall contract situation, contract risk warning, follow-up market development, resource assurance, resource allocation, talent training, safety and quality target control and measures, environmental protection laws and regulations, green construction site creation, technical construction plans, high-tech, intelligent software applications and needs The problems that can be solved by project coordination, etc.
    , can be solved on the spot, and the problems that cannot be solved on the spot have a timetable, and the responsibility is assigned to the head, which lays the foundation for the high start of the project construction


    .


    The leaders of the Fourth Construction Company, the second-level units, and the personnel of the project department inspected the site, the office camp, and the prefabricated factory, and conducted docking discussions, including the determination of the project type, the planning and layout of temporary construction, the division of economic responsibilities for large-scale machinery, material procurement, equipment allocation management, Overall contract situation, contract risk warning, follow-up market development, resource assurance, resource allocation, talent training, safety and quality target control and measures, environmental protection laws and regulations, green construction site creation, technical construction plans, high-tech, intelligent software applications and needs The problems that can be solved by project coordination, etc.
    , can be solved on the spot, and the problems that cannot be solved on the spot have a timetable, and the responsibility is assigned to the head, which lays the foundation for the high start of the project construction

    .
    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.