Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
The 50MW grid-connected photovoltaic power generation project of Golmud Phase III of Guodian Qinghai Branch was successfully connected to the grid at 15:12 on June 14, 2016, and the operation is good
.
The smooth commissioning of the project marks that the installed capacity of photovoltaic power generation of Qinghai Company has exceeded 150MW
.
The project was approved by the group company on March 8, 2016, and officially started on
March 15.
In the face of the three unfavorable factors of short production period of "6.
30", tight seller's market resources during the construction period and difficult construction in the plateau special environment, Qinghai Company made concerted efforts to fully maintain the state of lack of oxygen and spirit, firmly determined that Qingshan did not relax, carried out work creatively, actively strengthened peripheral communication and coordination, scientifically strengthened on-site construction management, effectively ensured the supply of equipment and materials, so that the project construction could be efficiently promoted, connected to the grid 16 days earlier than the original plan, and the investment was about
50 million yuan lower than the plan 。 The project has achieved "three" successes in grid-connected acceptance, reverse power transmission and grid-connected start-up and three "optimal" cost, quality and construction period in the same period, creating a benchmark for similar projects
.
The 50MW grid-connected photovoltaic power generation project of Golmud Phase III of Guodian Qinghai Branch was successfully connected to the grid at 15:12 on June 14, 2016, and the operation is good
.
The smooth commissioning of the project marks that the installed capacity of photovoltaic power generation of Qinghai Company has exceeded 150MW
.
The project was approved by the group company on March 8, 2016, and officially started on
March 15.
In the face of the three unfavorable factors of short production period of "6.
30", tight seller's market resources during the construction period and difficult construction in the plateau special environment, Qinghai Company made concerted efforts to fully maintain the state of lack of oxygen and spirit, firmly determined that Qingshan did not relax, carried out work creatively, actively strengthened peripheral communication and coordination, scientifically strengthened on-site construction management, effectively ensured the supply of equipment and materials, so that the project construction could be efficiently promoted, connected to the grid 16 days earlier than the original plan, and the investment was about
50 million yuan lower than the plan 。 The project has achieved "three" successes in grid-connected acceptance, reverse power transmission and grid-connected start-up and three "optimal" cost, quality and construction period in the same period, creating a benchmark for similar projects
.