    Guangdong Qingyuan Pumped Storage Power Station Unit 2 pumping started successfully

    • Last Update: 2022-11-20
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    Recently, Unit 2 of Guangdong Qingyuan Pumped Storage Power Station, to which the South Grid belongs, successfully started pumping, marking the final stage of the commissioning of the conventional project of Unit 2
    .
    Since the start of the commissioning of the unit, most of the commissioning projects have passed at one time, which is better than the excellent level
    in the national standard.

    It is understood that from the tailwater cone to the generator rotor yoke, all large components of Qingyuan pumped storage power station are pre-assembled in the factory, and problems are detected in advance and dealt with in the factory to ensure zero defects of factory products and one-time success of on-site assembly
    .
    In the equipment installation stage, all participants in the construction of the Qingshu power station fully carry forward the team spirit, work together, strictly control the installation quality, and all installed projects pass the acceptance
    at one time.

    Recently, Unit 2 of Guangdong Qingyuan Pumped Storage Power Station, to which the South Grid belongs, successfully started pumping, marking the final stage of the commissioning of the conventional project of Unit 2
    .
    Since the start of the commissioning of the unit, most of the commissioning projects have passed at one time, which is better than the excellent level
    in the national standard.

    Qingyuan pumped storage power station

    It is understood that from the tailwater cone to the generator rotor yoke, all large components of Qingyuan pumped storage power station are pre-assembled in the factory, and problems are detected in advance and dealt with in the factory to ensure zero defects of factory products and one-time success of on-site assembly
    .
    In the equipment installation stage, all participants in the construction of the Qingshu power station fully carry forward the team spirit, work together, strictly control the installation quality, and all installed projects pass the acceptance
    at one time.

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.