Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
The quadruple heat exchanger hoisted this time has a diameter of 6.
6 meters, a length of 56.
5 meters and a weight of 1,656 tons.
It is the core equipment of the styrene unit of Guangdong Petrochemical's refining and chemical integration project, and it is also the last thousand-ton equipment of Guangdong Petrochemical
.
On the hoisting site, the CNPC First Construction Guangdong Petrochemical large-scale hoisting project team used two crawler cranes of 4,000 tons and 1,600 tons, and adopted the "dual-host direct lifting method".
It only took less than two hours, and the equipment was stably in place
.
It is understood that it only took 4 days for the equipment to be unloaded at the port of the Guangdong Petrochemical Project Product Terminal on the morning of July 14 to the completion of the whole process of transportation and hoisting.
The world's largest quadruple heat exchanger for styrene equipment was successfully placed in the "new home"
.
In order to ensure the smooth implementation of hoisting and gain time for the project to be handed over and put into production, the large-scale hoisting project of CNPC First Construction Guangdong Petrochemical Co.
, Ltd.
overcomes the short time required for the crane to enter the factory, the reserved hoisting site is small, and the foundation treatment is difficult (there are buried parts, Manholes) and many other difficulties, the "4×24" shift operation method effectively ensures the rapid and safe placement of the equipment
.
With the stable placement of the quadruple heat exchanger, the integrated hoisting project of the large-scale equipment of the Guangdong Petrochemical Refining and Chemical Integration Project was successfully concluded
.
The quadruple heat exchanger hoisted this time has a diameter of 6.
6 meters, a length of 56.
5 meters and a weight of 1,656 tons.
It is the core equipment of the styrene unit of Guangdong Petrochemical's refining and chemical integration project, and it is also the last thousand-ton equipment of Guangdong Petrochemical
.
On the hoisting site, the CNPC First Construction Guangdong Petrochemical large-scale hoisting project team used two crawler cranes of 4,000 tons and 1,600 tons, and adopted the "dual-host direct lifting method".
It only took less than two hours, and the equipment was stably in place
.
It is understood that it only took 4 days for the equipment to be unloaded at the port of the Guangdong Petrochemical Project Product Terminal on the morning of July 14 to the completion of the whole process of transportation and hoisting.
The world's largest quadruple heat exchanger for styrene equipment was successfully placed in the "new home"
.
In order to ensure the smooth implementation of hoisting and gain time for the project to be handed over and put into production, the large-scale hoisting project of CNPC First Construction Guangdong Petrochemical Co.
, Ltd.
overcomes the short time required for the crane to enter the factory, the reserved hoisting site is small, and the foundation treatment is difficult (there are buried parts, Manholes) and many other difficulties, the "4×24" shift operation method effectively ensures the rapid and safe placement of the equipment
.
With the stable placement of the quadruple heat exchanger, the integrated hoisting project of the large-scale equipment of the Guangdong Petrochemical Refining and Chemical Integration Project was successfully concluded
.
.
Among them, there are 28 sets of equipment above 1,000 tons, with a total hoisting weight of about 77,000 tons, creating a new record for the integrated hoisting of the whole plant
.
.
Among them, there are 28 sets of equipment above 1,000 tons, with a total hoisting weight of about 77,000 tons, creating a new record for the integrated hoisting of the whole plant
.
.
Among them, there are 28 sets of equipment above 1,000 tons, with a total hoisting weight of about 77,000 tons, creating a new record for the integrated hoisting of the whole plant
.
.
Among them, there are 28 sets of equipment above 1,000 tons, with a total hoisting weight of about 77,000 tons, creating a new record for the integrated hoisting of the whole plant
.
.
Among them, there are 28 sets of equipment above 1,000 tons, with a total hoisting weight of about 77,000 tons, creating a new record for the integrated hoisting of the whole plant
.
.
Among them, there are 28 sets of equipment above 1,000 tons, with a total hoisting weight of about 77,000 tons, creating a new record for the integrated hoisting of the whole plant
.
.
Among them, there are 28 sets of equipment above 1,000 tons, with a total hoisting weight of about 77,000 tons, creating a new record for the integrated hoisting of the whole plant
.