Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
On April 26, the 1# boiler in the power center of the Guangdong Petrochemical Refining and Chemical Integration Project, which was built by Huanqiu, was successfully ignited, laying the foundation for the next pipeline purging and steam turbine running, marking the power center from engineering The construction phase is transferred to the production start-up phase
The power center is the source of ultra-high pressure steam power for the entire project, including 4 sets of 450 t/h high temperature and ultra-high pressure gas boilers and 3 steam turbine generator sets, supporting flue gas denitrification and environmental protection facilities to achieve "clean" flue gas emissions.
The power center is under the general contract of PC of Huanqiu Company, and jointly implemented by Huanqiu Guangdong Company and Huanqiu Jilin Chemical Construction
After the boiler entered the stage of full-scale installation, problems such as the narrow construction site, frequent cross operations, many high-altitude operations, and the epidemic affecting the supply of materials followed one after another, posing huge challenges to the on-site construction
In order to ensure the smooth realization of the boiler ignition goal, the joint management team of Huanqiu Guangdong Company and Huanqiu Jilin Chemical Construction has built a community of responsibility, made arrangements in advance, carefully organized, and implemented the spirit of the group company's special promotion meeting on Guangdong Petrochemical Project Engineering Construction and Production Operation on April 15.
The project department insisted on holding daily meetings to overcome technical difficulties and efficiently solve various problems, and successfully completed the single-machine fan test, boiler chemical cleaning, boiler air pressure test and other work, creating a prerequisite for the boiler to achieve high-quality ignition