    Four sets of equipment of Ningbo Engineering Gulei Project were handed over

    • Last Update: 2021-08-04
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    China Petrochemical News Network reported on July 31, Gulei Petrochemical held a plant delivery ceremony, the general contract of the Gulei Project Department of Ningbo Engineering Company of Refining & Chemical Engineering Group Co.
    , Ltd.
    Four sets of devices have achieved high-standard delivery
    .

    The steam-power cogeneration unit began piling on January 1, 2019, civil construction began on May 11, 2019, and installation began on August 28, 2019; process surplus materials and hazardous waste equipment in the whole plant began in September 2019 Piling began on the 23rd, civil construction began on October 28, 2019, and installation work began on April 6, 2020; the fuel storage facility began piling on February 23, 2019, and civil construction and installation began on July 18, 2019 Work will begin on March 21, 2020
    .

    After the on-site installation started, the company's Gulei project department overcame the impact of the new crown pneumonia epidemic and successively carried out a number of labor competitions and accelerated on-site construction.
    On May 21, 2020, the 240-meter-high chimney construction was completed 40 days in advance; December 2020 On the 31st, the high-temperature oven of the No.
    2 boiler of the cogeneration unit was started; on March 15, 2021, the high-temperature oven of the No.
    3 boiler of the cogeneration unit was started; on May 25, 2021, the No.
    1 steam turbine generator set One turn was successful; on 27th, 2021, the No.
    1 boiler started the high-temperature oven, achieving the 5.
    30 target 3 days in advance
    .


    On July 10, 2021, the steam-power co-generation plant sent another good news on the spot: the No.


    In the meantime, 270,636 cubic meters of earthwork, 1,370,65 cubic meters of concrete were poured, 14430 tons of steel bars were installed, 13,793 tons of steel structures were installed, 441 sets of equipment and pipelines were installed.


      As of July 30, 2021, civil engineering, installation, pipeline pressure test, stand-alone test run, instrument commissioning, oven, heat preservation and other work have been completed.


      (Yang Li)

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.