    ExxonMobil Huizhou Complex Project, CNOOC/Shell Phase III Project

    • Last Update: 2022-08-17
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    In terms of the petrochemical energy and new material industry, the comprehensive strength of Huizhou Daya Bay Petrochemical Zone has jumped to the first place in the national chemical industry pa.


    Recently, the ExxonMobil Huizhou Chemical Complex Project and the CNOOC/Shell Phase III Project, which have attracted much attention from the industry, have made new progre.


    On the website of Huizhou Daya Bay Economic and Technological Development Zone, the "One Announcement of the EIA of the Supporting Terminal of the ExxonMobil Huizhou Chemical Complex Project" and the "One Announcement of the Marine EIA of the Subsea Pipeline Relocation Project of the CNOOC/Shell Phase III Projec.


    An environmental impact assessment of the supporting terminal of the ExxonMobil Huizhou Chemical Complex Project shows that in order to ensure the transportation of heavy items for the ExxonMobil Huizhou Chemical Complex Project, ExxonMobil (Huizhou) Chemical .


    CNOOC/Shell Phase III Subsea Pipeline Routing Relocation Project A public announcement of the marine environmental impact assessment of Huade Petrochemical submarine pipeline shows that the proposed Huade submarine cable project is located in the sea area between Mabianzhou and Petrochemical Park in Daya Bay, Guangdong Province, starting at Mabianzhou Near the launching point of the original oil pipeline, the landing point directly landed on the existing Haibin Aven.


    ExxonMobil Huizhou Chemical Complex Project Introduction

    The total investment of ExxonMobil Huizhou chemical complex project is about 10 billion US dolla.


    The raw material of the project is crude oil, and crude oil desalination, ethylene and downstream deep processing projects will be construct.


    It is reported that the first phase of the project plans to build 12 sets of process units, including crude oil desalination, ethylene cracking, LDPE, LLDPE, PP, butadiene extraction, aromatic extraction, butene-1, pyrolysis gasoline hydrogenation, diisobutene, chemical cleaning Fuel, sulfur recovery combined devices, e.


    Huizhou CNOOC/Shell Phase III Project

    Before the Sino-Dutch Economic and Trade Forum held on October 16, 2018, the leaders of China and the Netherlands witnessed the signing of 8 cooperation agreements between the companies of the two sides, involving energy, finance, aviation, agricultural technology and other fields, with a total amount of about 10 billion US dolla.


    Among them, CNOOC and Royal Dutch Shell signed a memorandum of understanding on the cooperation of the Huizhou petrochemical project in The Hague, and decided to build the third phase of the project in China with a total investment of several billion US dolla.


    This signing is the third time that CNOOC and Shell have joined hands after the Phase I and Phase II of the Daya Bay Petrochemical Proje.


    According to the "2019 Key Project Plan" issued by the Guangdong Provincial Development and Reform Commission:

    Construction content and scale: 5 million tons/year ethylene, supporting 10 million tons/year oil refining

    Estimated total investment: 4600000000 yuan

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.