Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
On August 2, the Bao 8-1 Ping 3 well located in Fugu County, Shaanxi Province, was successfully drilled to 1,711 meters, marking the first 100 million cubic meters of coal-bed methane development project on a large scale in China to complete the drilling task efficiently
.
The Bao 8 coalbed methane development project is a coalbed methane rolling edge expansion project deployed by CNPC CBM in the Baode block of the Edong gas field
.
Exploration data show that there are two main coal seams developed in this area, No.
4+5 and No.
8+9.
On this basis, the geology and engineering technicians of the CBM company have gone through 10 on-site surveys and 11 rounds of optimized deployment, and compiled the first domestic development plan for a large CBM platform with a capacity of 100 million cubic meters
.
The plan is developed in the form of 4 large-platform horizontal wells with long horizontal sections to solve the problem of difficult development of urban overlying coalbed methane resources
At present, the 35 cluster wells of the Bao 8 CBM development project have a coal seam encounter rate of 100%.
The average horizontal section of 20 horizontal wells is 976 meters long.
The coal seam encounter rate has reached 98.