    China Southern Power Grid's "Hainan Interconnection Second Round" project is expected to lay submarine cables in November

    • Last Update: 2022-11-26
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    On the morning of the 10th, the People's Government of Hainan Province organized a mobilization meeting for the construction of submarine cable laying facilities for the main network of China Southern Power Grid and the second interconnection project of Hainan Power Grid (hereinafter referred to as "Hainan Network Second Round"), organized various departments in Guangdong and Hainan provinces to work together to do a good job in organizational management and safety control during submarine cable construction, ensure the safety and order of marine traffic in the Qiongzhou Strait during construction, and ensure the smooth progress
    of the construction of submarine cable laying facilities of the second round of Hainan Interconnection Project.
    It is reported that the land project of "Hainan Network Second Round" has been fully completed and put into operation at the end of May this year, and the laying of submarine cables in the most critical link of the project is expected to start in November
    .

    It is understood that the "Hainan Network Second Round" is a key project in Hainan Province and Guangdong Province, with a total investment of 3.
    284 billion yuan
    .
    The project started in October 2015, the land works, including overhead transmission lines and substation works, were fully completed and put into operation at the end of May this year, and the submarine cable laying will start in November, which is the most critical part of
    the project.

    The submarine cable adopts 500 kV oil-filled paper insulated cable, with a single continuous length of about 31 kilometers, which is currently the longest submarine cable of the same type in the world, and there is no domestic production capacity and construction capacity
    .
    At present, the shipping schedule for the installation of facilities has been set from October this year to January next year
    .
    Since the submarine cable crosses the Qiongzhou Strait, the laying work must be carried out continuously without stopping, and the cooperation and support of the Maritime Safety Bureau and local governments are required to ensure the safety of passing ships and construction, and ensure that construction operations are not interfered with
    by fishing activities.

    At the mobilization meeting, the South China Sea Branch of the State Oceanic Administration, the Chengmai County Government of Hainan Province, the Hainan Maritime Safety Bureau, the Hainan Provincial Coastal Defense and Port Office, the Zhanjiang Municipal Government of Guangdong Province, the Xuwen County Government and other government departments expressed their views, expressing their full support for the construction of the "Hainan Network Second Circuit", creating a good external environment, and ensuring that the construction of submarine cable laying facilities is carried out
    as planned.
    China Southern Power Grid Corporation will coordinate the internal resources, grasp the project progress, safety and quality management, and promote the commissioning of the second cycle of the interconnection project on schedule
    .

    Since June 2009, after the "Hainan Interconnection One" was put into operation, Hainan has completely ended the history of
    power island operation.
    With the rapid social and economic development of Hainan, the construction of the second phase of Hainan nuclear power project, especially the construction of Hainan Free Trade Zone (Port), the original single-loop network can no longer meet the needs
    of power supply and power grid system in Hainan Province.
    After the completion of the second cycle of the Hainan interconnection project, the double-loop line interconnection between the Hainan power grid and the southern main network will be realized, and the power transmission capacity will be increased from 600,000 kilowatts to 1.
    2 million kilowatts, which will further improve the reliability of the interconnection project, provide a "double guarantee" for the safety of the power grid and the stable operation of nuclear power in Hainan Province, help Hainan build a green energy island, and provide strong power support
    for the construction of the Hainan Free Trade Zone (port).

     

    On the morning of the 10th, the People's Government of Hainan Province organized a mobilization meeting for the construction of submarine cable laying facilities for the main network of China Southern Power Grid and the second interconnection project of Hainan Power Grid (hereinafter referred to as "Hainan Network Second Round"), organized various departments in Guangdong and Hainan provinces to work together to do a good job in organizational management and safety control during submarine cable construction, ensure the safety and order of marine traffic in the Qiongzhou Strait during construction, and ensure the smooth progress
    of the construction of submarine cable laying facilities of the second round of Hainan Interconnection Project.
    It is reported that the land project of "Hainan Network Second Round" has been fully completed and put into operation at the end of May this year, and the laying of submarine cables in the most critical link of the project is expected to start in November
    .

    Submarine cables

    It is understood that the "Hainan Network Second Round" is a key project in Hainan Province and Guangdong Province, with a total investment of 3.
    284 billion yuan
    .
    The project started in October 2015, the land works, including overhead transmission lines and substation works, were fully completed and put into operation at the end of May this year, and the submarine cable laying will start in November, which is the most critical part of
    the project.

    The submarine cable adopts 500 kV oil-filled paper insulated cable, with a single continuous length of about 31 kilometers, which is currently the longest submarine cable of the same type in the world, and there is no domestic production capacity and construction capacity
    .
    At present, the shipping schedule for the installation of facilities has been set from October this year to January next year
    .
    Since the submarine cable crosses the Qiongzhou Strait, the laying work must be carried out continuously without stopping, and the cooperation and support of the Maritime Safety Bureau and local governments are required to ensure the safety of passing ships and construction, and ensure that construction operations are not interfered with
    by fishing activities.

    At the mobilization meeting, the South China Sea Branch of the State Oceanic Administration, the Chengmai County Government of Hainan Province, the Hainan Maritime Safety Bureau, the Hainan Provincial Coastal Defense and Port Office, the Zhanjiang Municipal Government of Guangdong Province, the Xuwen County Government and other government departments expressed their views, expressing their full support for the construction of the "Hainan Network Second Circuit", creating a good external environment, and ensuring that the construction of submarine cable laying facilities is carried out
    as planned.
    China Southern Power Grid Corporation will coordinate the internal resources, grasp the project progress, safety and quality management, and promote the commissioning of the second cycle of the interconnection project on schedule
    .

    Since June 2009, after the "Hainan Interconnection One" was put into operation, Hainan has completely ended the history of
    power island operation.
    With the rapid social and economic development of Hainan, the construction of the second phase of Hainan nuclear power project, especially the construction of Hainan Free Trade Zone (Port), the original single-loop network can no longer meet the needs
    of power supply and power grid system in Hainan Province.
    After the completion of the second cycle of the Hainan interconnection project, the double-loop line interconnection between the Hainan power grid and the southern main network will be realized, and the power transmission capacity will be increased from 600,000 kilowatts to 1.
    2 million kilowatts, which will further improve the reliability of the interconnection project, provide a "double guarantee" for the safety of the power grid and the stable operation of nuclear power in Hainan Province, help Hainan build a green energy island, and provide strong power support
    for the construction of the Hainan Free Trade Zone (port).

     

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.