    Home > Chemicals Industry > Chemical Technology > Chengdu's fiber network coverage reached 100%, and copper cables were officially phased out

    Chengdu's fiber network coverage reached 100%, and copper cables were officially phased out

    • Last Update: 2022-11-19
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    On the afternoon of September 9, the program-controlled switch of China Telecom Chengdu Second Communication Hub Building was turned off and the "Bison 817" program-controlled terminal bureau was withdrawn from operation, which means that the coverage of Chengdu's optical fiber network reached 100%, and copper cables were officially eliminated
    .

    It is understood that the "Besen 817" program-controlled terminal bureau located on the second floor of the hub building was built in April
    2004.
    Chen Yu, a network engineer, is one of the core members of the "All-Optical Chengdu" project team of China Telecom Chengdu Branch, and has led the completion of 21 terminal bureaus to shut down and decommission the network
    .
    He said: "Every batch of users from copper cable to fiber network cutover work is like a precision surgical operation, we must pay attention to every detail to strive to give users the best network awareness
    .
    " ”

    Up to now, Chengdu's optical fiber network has covered more than 6.
    37 million households, and the fiber-to-the-home rate in urban areas and first- and second-class townships is 100%.

    On the afternoon of September 9, the program-controlled switch of China Telecom Chengdu Second Communication Hub Building was turned off and the "Bison 817" program-controlled terminal bureau was withdrawn from operation, which means that the coverage of Chengdu's optical fiber network reached 100%, and copper cables were officially eliminated
    .

    Fiber optic network

    It is understood that the "Besen 817" program-controlled terminal bureau located on the second floor of the hub building was built in April
    2004.
    Chen Yu, a network engineer, is one of the core members of the "All-Optical Chengdu" project team of China Telecom Chengdu Branch, and has led the completion of 21 terminal bureaus to shut down and decommission the network
    .
    He said: "Every batch of users from copper cable to fiber network cutover work is like a precision surgical operation, we must pay attention to every detail to strive to give users the best network awareness
    .
    " ”

    Up to now, Chengdu's optical fiber network has covered more than 6.
    37 million households, and the fiber-to-the-home rate in urban areas and first- and second-class townships is 100%.

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.