    Can the later stage of the PP maintenance and production game bring opportunities?

    • Last Update: 2022-08-16
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    Since 2020, the maintenance projects of petrochemical plants have been carried out in an orderly manner, and it is estimated that the shortage of resources will be about 886,100 to.


    Table 1 Plant shutdown and maintenance schedule

    petrochemical nameParking capacityReason for Parkingparking timedriving time
    Shenhua Yulin300,000 tons/yearParking for maintenance2020-4-6Expected 55 days
    Dalian Organic270,000 tons/yearParking for maintenance2020-5-10Expected 50 days
    Dushanzi PetrochemicalOld line 70,000 tons/yearParking for maintenance2020-4-15pending
    Pucheng Clean Energy400,000 tons/yearParking for maintenance2020-5-11pending
    Zhongsha Tianjin450,000 tons/yearParking for maintenance2020-5-92020-7-10
    Tianjin United60,000 tons/yearParking for maintenance2020-5-82020-7-8
    Shenhua Xinjiang450,000 tons/yearParking for maintenance2020-5-18Plan to drive at the end of the month
    Zhenhai RefineryLine 1: 200,000 tons/yearParking for maintenance2020-5-202020-6-28
    Petrochemical name Parking capacity Parking reasons Parking time Driving time Shenhua Yulin 300,000 tons/year parking maintenance 2020-4-6 Expected 55 days Dalian organic 270,000 tons/year parking and maintenance 2020-5-10 Expected 50 days Dushanzi Petrochemical old line 7 10,000 tons/year for maintenance 2020-4-15 To be determined Pucheng Clean Energy 400,000 tons/year for maintenance2020-5-11 To be determined Zhongsha Tianjin 450,000 tons/year for maintenance2020-5-92020-7-10Tianjin United 60,000 tons/year for maintenance2020-5-82020-7-8Shenhua Xinjiang 450,000 tons/year for maintenance2020-5-18 Plan to start Zhenhai Refinery Line 1 200,000 tons/year for maintenance2020-5-202020 -6-28 Petrochemical Name Parking Capacity Parking Reason Parking Time Driving Time Petrochemical Name Parking Capacity Parking Reason Parking Time Driving Time Shenhua Yulin 300,000 tons/year Parking Maintenance 2020-4-6 It is estimated that Dalian organic 270,000 tons/year will be shut down for maintenance in 55 da.



    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.