    Brazil's new tender for transmission lines is scheduled for Dec. 19

    • Last Update: 2023-01-02
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    Brazilian power agency Aneel recently said that the next round of transmission line tenders will begin on December 19 and is expected to generate $1 billion in investment
    .

    The new round of tenders will involve 12 states, adding 2,470 kilometers of new transmission lines and adding 7,800 MVA
    in transmission capacity.
    It is reported that the scale of this round of bidding is significantly smaller than the same period last year, and in December last year, 7,152 kilometers of transmission lines and 14,819 MVA capacity were signed, involving 13 states and a total investment of more than 3.
    2
    billion US dollars.

    Aneel has approved a new round of tender rules, under which the successful bidder will be awarded a concession contract for up to 30 years, including the construction, operation and maintenance of transmission lines and associated substations
    .

    Brazilian power agency Aneel recently said that the next round of transmission line tenders will begin on December 19 and is expected to generate $1 billion in investment
    .

    Aneel transmission lines 1219 10

    The new round of tenders will involve 12 states, adding 2,470 kilometers of new transmission lines and adding 7,800 MVA
    in transmission capacity.
    It is reported that the scale of this round of bidding is significantly smaller than the same period last year, and in December last year, 7,152 kilometers of transmission lines and 14,819 MVA capacity were signed, involving 13 states and a total investment of more than 3.
    2
    billion US dollars.

    1224707800MVA12715214,819MVA1332

    Aneel has approved a new round of tender rules, under which the successful bidder will be awarded a concession contract for up to 30 years, including the construction, operation and maintenance of transmission lines and associated substations
    .

    Aneel30

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.