    BP-led Tortue FLNG project phase 1 completed 58%

    • Last Update: 2021-06-07
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    Sinopec News Network reported on May 10 that the BP-led Greater Tortue Ahmeyim LNG project on the maritime border of Mauritania and Senegal is underway.


    Dallas-based Kosmos Energy notified that the first phase of the project was 58% completed by the end of the first quarter.


    Cosmos Energy reported on Monday that progress has been made in all major work processes, including FPSOs, floating LNG vessels, hub terminals (concrete breakwaters) and subsea infrastructure.


    The partner’s goal is to complete 80% of the first phase by the end of the year.


    According to Cosmos, as previously communicated, the sale and leaseback of FPSO will be completed in the second quarter of 2021.


    The Greater Tortue Ahmeyim project will produce natural gas from ultra-deep water subsea systems and mid-floating production, storage and offloading (FPSO) vessels that will process natural gas to remove heavier hydrocarbon components.


    Subsequently, the natural gas will be transferred to a floating liquefied natural gas (FLNG) facility located in offshore hubs in Mauritania and Senegal.


    BP has reached a 20-year deal with Golar's Gimmi FLNG to provide services for it.


      The FLNG facility is designed to provide an average of about 2.


      The project is the first major natural gas project in the basin to obtain FID.


      Hao Fen Translated from Offshore Energy

      The original text is as follows:

      BP-led Tortue FLNG project's Phase 1 58 pct done

      The BP-led Greater Tortue Ahmeyim LNG project on the maritime border of Mauritania and Senegal is progressing.


      Dallas-based Kosmos Energy informed the project's Phase 1 was 58 per cent done at the end of the first quarter.


      On Monday Kosmos Energy reported material progress across all of the major workstreams, including the FPSO, Floating LNG vessel, hub terminal (concrete breakwater) and subsea infrastructure.


      The partnership is targeting Phase one to be around 80% complete by year end.


      Kosmos expects completion of the FPSO sale and lease-back in the second quarter of 2021 as previously communicated.


      The Greater Tortue Ahmeyim project will produce gas from an ultra-deepwater subsea system and mid-water floating production, storage and offloading (FPSO) vessel, which will process the gas, removing heavier hydrocarbon components.


      The gas will then be transferred to a floating liquefied natural gas (FLNG) facility at a nearshore hub located on the Mauritania and Senegal maritime border.

      BP has secured the services of Golar's Gimmi FLNG on a 20-year deal.
    The pair agreed a delay in delivery of the vessel due to the effects of the Coronavirus pandemic.
    BP now expects the delivery of the in 2023, the same year when the project is expected to produce the first gas.

      The FLNG facility is designed to provide circa 2.
    5 million tonnes of LNG per annum on average, with the total gas resources in the field estimated to be around 15 trillion cubic feet.

      The project, the first major gas project to reach FID in the basin, is planned to provide LNG for global export as well as making gas available for domestic use in both Mauritania and Senegal.

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.