Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
The power station unit of the caprolactam industrial chain relocation, upgrading and transformation development project of Baling Petrochemical Company was undertaken by Sinopec Fifth Construction Co.
At present, the project has installed 2,864 tons of boiler steel structure, with a completion rate of 46.
At present, the project has installed 2,864 tons of boiler steel structure, with a completion rate of 46.
37%; installed 882 tons of air preheaters, with a completion rate of 43.
88%; installed 210 tons of water walls, with a completion rate of 27.
52%; installed 113 tons of economizers, with a completion rate of 7.
59% ; 48 tons of superheater were installed, and the completion rate was 5.
35%
.
At the beginning of the new year, Sinopec Fifth Construction Company has nearly 430 builders working at the power station site of the project every day, making every effort to promote the safe and high-quality construction of the project
.