Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
Sinopec News Network reported on September 24, at the construction site of Baling Petrochemical’s Caprolactam Industrial Chain Relocation and Upgrading Transformation Development Project Department, the construction site of the front area of the plant is under construction for steel bar binding.
The materials on the construction site are stacked neatly and orderly, and the slope of the foundation pit It is covered with colored striped cloth, and the earthwork on the side is covered with a dust-proof net
.
The quality of the work processes such as cushioning, strip foundation pouring, and steel tying is good .
Baling Petrochemical’s caprolactam industrial chain relocation project department created a "model room" to build a high-quality project.
By creating a model and summarizing practices, the "national excellent project" was regarded as the expected use function and quality standard for project construction, and the quality "process model" and "model" were promoted.
"Model project" construction, organize various contractors to build the "first delivery model" for scaffolding, steel tying, concrete pouring and other processes.
After acceptance, take pictures and record the construction quality and solidify it as a template.
Follow-up similar operations are required to be implemented in accordance with the model to ensure construction Quality
.
The caprolactam industrial chain relocation and upgrading transformation development project is a "dual key" construction project between Hunan Province and Sinopec.
The Relocation Project Department implements standardized management of the construction site in accordance with the requirements of "Sinopec Construction Project Perceptual Quality Improvement" and "Green Construction Site" creation requirements
.
During the construction work of the model project, the project department, project branch, supervision company, and construction unit are relocated to strictly manage construction and quality control, strengthen construction organization and coordination, and combine the characteristics of the project to prepare construction plans and carry out plans to ensure that the construction personnel and The monitoring personnel fully understand the construction points and precautions
.
They also strengthened the inspection of the construction process, changed the project quality control from static management to dynamic control, announced in detail the template standards for more complex nodes and parts, and carried out on-site physical presentations.
The contractor strictly carried out the construction according to the lofting drawing, so that the operators could construct.
"There are basis, methods, and standards; to strengthen the inspection and acceptance of concealed projects, strictly manage the entire process of quality acceptance, and implement the "three inspection system" of self-inspection, other inspections and special inspections.
The project department, the supervision company, and the quality supervision The station
conducts joint inspections in accordance with the process nodes, and can enter the next process after the acceptance is passed to ensure that each process meets the predetermined quality standard .
(Xia Qin, Li Yijun)