Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
11 Yue 29 days, South of the company to complete the ammonia system for a period of 45 days overhaul, the first time after a successful car repair, 12 Yue 2 Ri output of qualified liquid ammonia.
11 Yue 29 days, South of the company to complete the ammonia system for a period of 45 days overhaul, the first time after a successful car repair, 12 Yue 2 Ri output of qualified liquid ammonia.
On November 18th , the company's air separation steam turbine compressor was successfully commissioned.
“The air separation unit is the most difficult to maintain and has the highest technical requirements among the large units of the company.
Since October last year , they have overcome difficulties such as incomplete original data.
Lifting the upper cylinder head of the compressor was the first problem they encountered.
Air separation unit has nearly 40 important technical parameters, nearly 20 Ge A class quality monitoring points.
After taking down the air separation unit, they also achieved 100% independent overhaul of moving equipment.