    Home > Chemicals Industry > China Chemical > "14th Five-Year Plan" Another 100 billion investment map - ultra-low emission transformation of coal-fired power units

    "14th Five-Year Plan" Another 100 billion investment map - ultra-low emission transformation of coal-fired power units

    • Last Update: 2022-05-20
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com
    [ Industry News of Chemical Machinery and Equipment Network ] At the National Coal Power "Three Reforms Linkage" linkage typical case and technology promotion conference held by the General Electric Power Planning and Design Institute, the Deputy Director of the National Energy Administration said, "By the end of 2021, China will achieve ultra-low The emission of coal-fired power units exceeds 1 billion kilowatts, the scale of energy-saving transformation is nearly 900 million kilowatts, and the scale of flexible transformation exceeds 100 million kilowatts .
    Air pollutants account for less than 10% of the total
    .

     
    Chemical Machinery and Equipment Network Industry Dynamic Chemical Machinery and Equipment "By the end of 2021, China's ultra-low emission coal-fired power units will exceed 1 billion kilowatts, the scale of energy-saving transformation will be nearly 900 million kilowatts, and the scale of flexible transformation will exceed 100 million kilowatts"
    Since China clearly proposed the 2030 "carbon peak" and 2060 "carbon neutral" goals in September 2020, all walks of life have put green and low-carbon transformation on the agenda.
    stand out
    .
    But at the same time, China's coal-dominated resource endowment determines that coal-fired power will still play an important role in ensuring energy security for a long period of time
    .
    Therefore, under the current situation, the transformation of coal power should not only ensure that the status of its ballast stone remains unchanged, but also firmly change the pace of shifting from main energy sources to support and strip power sources
    .

     

    Following the "Thirteenth Five-Year Plan" coal power "three reforms and linkages" (energy saving and carbon reduction reform, heating reform and flexibility reform) have achieved remarkable results, at the end of 2021, the National Development and Reform Commission and the National Energy Administration jointly issued the "National Coal The “Implementation Plan for the Transformation and Upgrading of Electric Power Units” specifies that during the “14th Five-Year Plan” period, 350 million kilowatts of energy-saving transformation, 200 million kilowatts of flexible transformation, and 50 million kilowatts of heating transformation will be implemented
    .
    According to this calculation, in the past five years, the ultra-low emission transformation of coal power can drive an effective investment of about 100 billion yuan
    .

     
    According to this calculation, in the past five years, the ultra-low emission transformation of coal power can drive an effective investment of about 100 billion yuan
    .

      So for enterprises, what are the "Nuggets" in this market?
     

      Specifically, the promotion of energy-saving and efficiency-enhancing upgrades for coal-fired power units has a strong demand for waste heat utilization at the cold end of boilers and steam turbines, high-temperature subcritical comprehensive upgrading, and clean utilization, which is beneficial for waste heat utilization, soot purification, desulfurization and denitrification, and carbon capture Seal up related equipment; carry out heating transformation of coal-fired power units, and there are many opportunities for the development of central heating, cogeneration and other modes; strict production energy consumption and emission access standards There is a need for conventional pollutant treatment such as soot, sulfur dioxide, nitrogen oxides,
    etc.

     

      At present, some enterprises have taken the lead in laying out the "one-stop" plan for the upgrading and transformation of coal-fired power units
    .
    In January this year, Shenergy Group, Shanghai Electric and other local state-owned enterprises joined forces to integrate professional forces in design, manufacturing, construction, and finance to develop the "Shanghai Plan" for the upgrading and transformation of customized coal-fired power units and the green transformation of coal-fired power plants.
    And signed cooperation agreements with Baosteel, State Power Investment Corporation, etc.
    , and strive to fully amplify the spillover effect of the program and promote it to the whole country
    .

     

      At the same time, the pressure of carbon emission reduction has also been given to coal power companies
    .
    Industry insiders said that although the research on low-carbon technologies related to coal-fired power has been carried out vigorously, there are still problems such as high energy consumption and high cost in production, and large-scale application is still difficult to achieve
    .
    Practitioners suggest that the policy level should first clarify the goal of coal power carbon reduction, and provide practical support to enterprises through subsidies, flexible electricity prices, carbon trading, etc.
    , to provide practical experience and guarantee for the research and development of carbon reduction technology in the industry
    .

     
    At the same time, the pressure of carbon emission reduction has also been given to coal power companies
    .

      Original title: "14th Five-Year Plan" Another 100 billion investment map - ultra-low emission transformation of coal-fired power units
    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.