Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
In the early morning of August 21st, the last structural parts of the steel structure project of the Washington State Convention Center annex built by Zhenhua Heavy Industry left Shanghai for Seattle, marking the successful completion of Zhenhua Heavy Industry's first foreign construction steel structure production project.
the project is another successful partnership with American Bridge, following the San Francisco-Oakland New Bay Bridge, the Las Vegas Ferris Wheel and the Queens ferry Bridge in the United Kingdom.
The company is responsible for the production and transportation of all about 20,000 tons of steel structure of the project, its materials, manufacturing, acceptance must comply with the United States steel structure manufacturing, acceptance standards, especially structural welding needs to comply with the American Welding Society (AWS) D1.8 welding specifications, in the design, welding process, production management and other processes of very high standards, to meet its high seismic requirements.
affected by the new coronary pneumonia outbreak, the last components of the project were already completed but could not be shipped as planned.
the joint efforts of the two sides, the project finally confirmed the relevant shipment at the end of July.
At the same time, the last batch of components of the shipping work is being carried out in a tight way, the project team members overcome the hot weather, personnel shortage and other difficulties, fighting a week to complete the last batch of structural parts of the ship shipment work.
, the project has shipped six ships with a total of 32,600 structural parts.
the project, located in Seattle, Washington, USA, covers an area of about 24,000 square meters, two floors underground and 14 floors above ground, and will become a local "new landmark" in Washington.
.