Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
The outbreak of new crown pneumonia has had a certain impact on China's economic development.
, the development of the epidemic has been gradually controlled, production enterprises have started after the festival to resume work.
The Working Committee of the Chemical Park of the China Petroleum and Chemical Industry Federation conducted telephone research on 45 chemical parks in China from February 18 to 19 to understand the situation and related problems of enterprises in the chemical parks.
the results of the survey in this edition for the benefit of readers.
The survey covered 45 chemical parks in 16 provinces and autonomous regions in Jiangsu, Zhejiang, Shandong, Guangdong, Fujian, Yunnan, Heilongjiang, Hebei, Henan, Gansu, Shanghai, Shaanxi, Liaoning, Ningxia, Guangxi and Sichuan, including 25 china Chemical Parks in 2019 and 7 Potential Top 10 Parks.
the major parks to accelerate the development of enterprise resumption of work is the hard truth, epidemic prevention is a hard task.
the main chemical parks to grasp the epidemic prevention, one hand to grasp the resumption of work and production of enterprises, to promote economic and social development.
As of February 19, there were 16 of the 32 Top 30 China Petroleum and Chemical Parks and Potential 10 Fortified Industrial Parks in 2019, with a return rate of more than 80%, 10 parks with a recovery rate of 50% to 79%, and 6 parks with a recovery rate of less than 50%.
results, the resumption rate of more than 50% of the park accounted for about 81% of the number of statistical parks.
Most of the enterprises that have started work in the load rate of more than 60%, Hangzhou Bay Shangyu Economic and Technological Development Zone, Maoming High-tech Industrial Development Zone by logistics, personnel return to work and other factors, the operating load rate of about 30% to 40%.
last week, the Sinopec Federation's park committee also conducted a survey of the operating load rate of enterprises in the chemical park, which was generally below 50% last week, compared with a sharp increase this week.
from the progress of resumption of work, the chemical park under investigation for enterprises have put forward the record of resumption of work and epidemic prevention requirements, requiring enterprises to meet the conditions before the resumption of work.
At present, the overall progress of enterprise resumption of work in an orderly manner, Quangang Petrochemical Industrial Park to protect enterprises before February 25 basically all resumption of work, Shanghai Chemical Industry Zone is currently 95% of the resumption rate, Zhenjiang New Area new materials industrial park regulations on the enterprise will be basically resumed before February 20, the rest of the enterprises started work as soon as possible before the end of February.
QuanHui Petrochemical Industrial Park regulations enterprises will be fully started by February 29, Anhui Huaibei new coal chemical synthetic materials base under construction 16 projects will be completed by February 20, Fujian Luzhou Gulei Port Economic Development Zone enterprises will resume work by March 31 at the latest.
by region, Jiangsu, Shandong and Zhejiang are major chemical provinces, and of the 45 chemical parks surveyed, 7 of the 8 Jiangsu chemical parks had a recovery rate of more than 70%.
8 home areas in Shandong Province and 7 home areas in Zhejiang Province, the rate of resumption of work is more than 60%.
the leading enterprises in each park have basically not stopped production or resumed production in full, the park gives priority to the approval of the production of epidemic prevention materials, people's livelihood protection products production enterprises to resume work applications.
in the construction of key projects are gradually resumed research shows that the construction of chemical projects under construction affected by the epidemic has been delayed, the main reasons are focused on the difficulty of returning to work, equipment transportation is blocked.
research shows that Huayi Phase I Industrial Gas Island project is scheduled to resume construction from February 25 onwards, according to the outbreak prevention and control, construction personnel return to the situation gradually resume the construction of various projects, planned to be completed by the end of this year.
Huayi Phase II 750,000 tons / year acrylic and downstream deep processing integration project and chlor-alkali project started construction on November 27, 2019, is currently preparing to resume pre-work materials preparation and epidemic prevention materials, gradually recall employees and do a good job of isolation, the initial plan is to resume construction in early March.
because some concrete, stone and other enterprises have not resumed work, construction materials supply is tight.
16 major industrial projects under construction undertaken by Shenghong Refinery, Satellite Petrochemical, China Chemical International and other enterprises in Lianyungang Petrochemical Industry Base will resume work by the end of February.
million-ton ethylene project at Gurley Petrochemicals is scheduled to resume on February 29.
construction of the second phase of the 40 million tons/year refining integration project of Zhejiang Petrochemical Is gradually being resumed.
400 workers are busy working at the construction site of the second phase of the ethylene plant at the petrochemical site.
affected by the outbreak, the recent inter-provincial traffic and water traffic control to and from Fish Mountain Island, lifting materials can not be delivered in a timely manner.
the construction content of the site is also adjusted to welding, basic grout and other details.
in the production at the same time, petrochemical base to do a good job of epidemic prevention, return to the island, all in the observation area after quarantine observation 14 days before the resumption of work.
the epidemic continued enterprises to face many difficulties after investigation of the park enterprises in the process of resumption of work and production of the main problems have the following aspects: First, affected by the outbreak, provincial personnel have difficulties in returning to work.
has a greater impact on the southern and coastal parks.
because some provincial personnel due to epidemic prevention and control can not return to the enterprise on time, can return to the enterprise personnel also need to be isolated for 14 days, during the isolation of wages issued, to the enterprise caused a lot of pressure.
is due to logistics control, upstream and downstream under-construction, raw material input and product export and sales are affected.
because raw materials can not be imported on time resulting in enterprises can not produce at full capacity is very common.
there are some enterprises because of the high load rate, but the product can not be shipped, resulting in the product inventory is full, need to find a new storage warehouse.
is the lack of protective materials, especially masks, mostly by the local government unified deployment, can be used for enterprises to resume work mask resources are very tight.
some parks require enterprises to start work need to be equipped with the necessary epidemic prevention materials, so some enterprises can not meet the conditions, can not resume work.
, the management committee and enterprise supporting the insufficient number of centralized observation points, etc. , to the enterprise with more employees put forward a greater challenge.
In addition, due to the impact of the epidemic, some research institutes, trade and other personnel-intensive enterprises, has not yet resumed work, only some staff to maintain basic office, resulting in some key project design, research and development progress slowed down, is expected to delay completion time.
according to the research, the park re-engineering institute is facing difficulties also present some characteristics: First, the construction project because of installation, equipment, construction materials, personnel, etc. can not be in place in time, the construction progress is generally affected.
Second, many of the employees in the eastern and southern coastal chemical parks are from other provinces, the difficulty of returning to work is greater, while most of the employees in Shandong Province are employees of the province, so the problem of personnel returning to work is not serious, Jiangsu, Zhejiang in the prevention of epidemic prevention and resumption of work measures taken earlier, personnel return to work is better.
, Shandong, Guangdong and other provinces in the province logistics basic impact is not large, cross-provincial logistics impact is greater.
research report shows that the enterprise's policy of re-employment has been loosened, such as some parks in Shandong Province have begun a "commitment to resume work" policy, that is, to resume work first, after approval.
Futian District of Shenzhen has also adopted a "return to work first, after approval" model.
Zhejiang and Guangdong provinces, the "snatching" policy, but also let countless netizens call hard core, Jiangxi Province announced the cancellation of the approval procedures for the resumption of work, the following week the park is bound to be full of energy, full recovery, and time race.
.