    A brief description of the production process of polyurethane prefabricated direct buried insulation pipe

    • Last Update: 2022-10-20
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com
    Polyurethane direct buried insulation pipe can be widely used in industrial and mining enterprises, petrochemical enterprises, urban central heating, pipe networks, residential communities and other fields throughout
    the country.
    Polyurethane direct buried insulation pipe produces high-density polyethylene outer protective pipe, and then pouring polyurethane rigid foam insulation layer in the gap between the polyethylene outer protective pipe and the steel pipe is what we often call the "two-step method"
    .
    Polyurethane direct buried insulation pipe production process: steel pipe rust removal - polyurethane foaming - forming - finished product detection - warehousing 1.
    Rust removal 2.
    Pipe piercing and bracket bundling: A.
    The high-density polyethylene outer protection pipe selected according to the core pipe and insulation layer →
    .
    B.
    After rust removal→ the steel pipe is bundled in sections (1.
    5 m/section)→ the bundled bracket core tube is threaded into the high-density polyethylene outer protection tube, and the exposed parts of both ends of the core tube are 150mm-250mm
    .
    C.
    Seal the chucks (inner or outer card) that conform to the core diameter and insulation thickness at both ends of the pipe and lock them tightly
    .
    Note: The structure, material, bundling method and compressive strength of the bracket should be selected
    according to the core diameter and design requirements.
    3.
    Polyurethane casting foaming: adjust the mixing ratio of the foaming machine to 1:1.
    05→ measure the flow rate of the equipment→ set the pouring time (feeding amount / flow).

    Open the pouring hole in the middle of the HDPE outer protective pipe after the pipe is plugged at both ends of the pipe→ insert the pouring nozzle of the mixing head of the foaming machine into the pouring hole→ the pouring → material plug plugs the pouring hole→ ripening→ disassemble the chuck head→ inspect → correct the feeding amount → finished product
    .
    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.