    Zhejiang Petrochemical Residue Hydrogenation Compressor Successfully Commissioned No-load

    • Last Update: 2021-08-08
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    China Petrochemical News Network reported on July 12 that the second phase of Zhejiang Petrochemical Project No.
    2 3 million tons/year slurry-bed residue hydrogenation unit of Zhejiang Petrochemical Engineering Co.
    , Ltd.
    contracted two reciprocating compressor units for a first-time test run with no load.
    It marks that the project’s compressor unit commissioning has entered the final sprint stage
    .

    It is understood that Zhejiang Petrochemical’s two 3 million tons/year slurry-bed residue hydrogenation plants have a total of 10 compressors, of which 4 are centrifugal compressors and 6 are reciprocating compressors.
    They are the core part of the plant and the entire One of the key lines of project construction
    .


    Since the start of the construction of the slurry-bed residue hydrogenation unit, the Phase II Project Department of Zhejiang Petrochemical Company of Zhejiang Petrochemical Company has closely followed the delivery status of the compressor units, organized the owners and supervisors to carry out strict unpacking inspections, and carried out several installation and construction plans for the compressor units.


    In the construction of the compressor unit, the participating employees strive for perfection, strictly control the quality of each construction process, and pre-judge, accurately investigate, and rectify the hidden dangers of construction quality in advance, creating favorable conditions for the compressor unit to achieve the commissioning node on schedule


    While doing a good job in the quality control of the compressor unit construction, the project department overcomes the impact of many unfavorable factors such as tight construction period, narrow construction work space, frequent cross-construction of various professions, etc.


    At present, the project department takes the opportunity of the successful no-load test run of the compressor unit to accelerate the progress of the later electrical instrument commissioning work, and go all out to lay a solid foundation for the smooth start-up of the two slurry-bed residue hydrogenation units


    (Tian Yuanwu)

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.