    Yulian 110kV dual-circuit power supply line project is handed over

    • Last Update: 2023-02-01
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    After 65 days of tough battles, the 110kV dual-circuit power supply line migration project of Yulin Refinery was recently completed at CCCC, which won valuable time
    for subsequent line building, line commissioning, and grid-connected power transmission operation.

    The project is a key project of Yanchang Petroleum Group, with a total investment of 49.
    11 million yuan
    .
    The 110kV double-return line passes through Yangqiao, Longzhou, Zhenjing, Zhangjiaban Street Office and other townships in Jingbian County, and newly built 98 base towers, 16.
    81km I.
    return overhead line, and 16.
    89km
    II return overhead line.

    Since the start of the project on November 4 last year, Yulian has carefully organized the construction, arranged professional and technical personnel to work shifts 24 hours a day, supervised the whole process, and required the construction to be carried
    out around the clock.
    During the construction period, Yulian responded to unfavorable factors such as epidemic control, tight construction period, long construction route, difficulty involving multiple external cooperation of village committees, and winter construction, and completed the first phase of construction nodes in only 23 days, and all 98 foundation towers were poured
    .

    During the project construction process, Yulian Project Management Center actively formulated the organization construction plan, strengthened coordination with government departments, and ensured the smooth progress of
    the project.
    Implement epidemic control measures, strengthen the management of construction personnel, and control the flow
    of personnel.
    Construction inverted construction period, track equipment and material ordering and procurement progress, and determine the arrival time
    .
    In order not to affect the construction, the person in charge of the project management center led the team to organize the construction and hold a regular meeting of the project at 8 p.
    m.
    every day to solve various problems
    in the construction in time.

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.