Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
After 65 days of tough battles, the 110kV dual-circuit power supply line migration project of Yulin Refinery was recently completed at CCCC, which won valuable time
for subsequent line building, line commissioning, and grid-connected power transmission operation.
The project is a key project of Yanchang Petroleum Group, with a total investment of 49.
11 million yuan
.
The 110kV double-return line passes through Yangqiao, Longzhou, Zhenjing, Zhangjiaban Street Office and other townships in Jingbian County, and newly built 98 base towers, 16.
81km I.
return overhead line, and 16.
89km
II return overhead line.
Since the start of the project on November 4 last year, Yulian has carefully organized the construction, arranged professional and technical personnel to work shifts 24 hours a day, supervised the whole process, and required the construction to be carried
out around the clock.
During the construction period, Yulian responded to unfavorable factors such as epidemic control, tight construction period, long construction route, difficulty involving multiple external cooperation of village committees, and winter construction, and completed the first phase of construction nodes in only 23 days, and all 98 foundation towers were poured
.
During the project construction process, Yulian Project Management Center actively formulated the organization construction plan, strengthened coordination with government departments, and ensured the smooth progress of
the project.
Implement epidemic control measures, strengthen the management of construction personnel, and control the flow
of personnel.
Construction inverted construction period, track equipment and material ordering and procurement progress, and determine the arrival time
.
In order not to affect the construction, the person in charge of the project management center led the team to organize the construction and hold a regular meeting of the project at 8 p.
m.
every day to solve various problems
in the construction in time.