    Yangnong Group's key construction projects steadily enter the fast lane

    • Last Update: 2022-06-27
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    Ruiheng Company- ECH Joint Project

    Rui Henggong Division -ECH joint project Rui Henggong Division -ECH joint projects

    Construction stage: R&D and design

    Construction stage: R&D and design

    The overall progress of the ECH project is proceeding in an orderly manner as planned.


    The overall progress of the ECH project is proceeding in an orderly manner as planned.


    At the same time, the project team connected with the design institute to complete the design and review of the project drawings; the project management team closely followed the preparation of the environmental impact assessment and safety assessment, and was recognized by the expert group at the environmental assessment and safety assessment review meeting in June .


    Project epoxy epoxy project

    Construction stage: preliminary design and preparation of budgetary estimates

    Construction stage: preliminary design and preparation of budgetary estimates

    The epoxy resin project completed the park feasibility study expert review and project filing in June , and the environmental impact assessment, safety assessment, and job evaluation contracts were signed; in July , it obtained the investment approval of Yangnong Group, completed the project design and process package opening; it is currently underway Preliminary design and preparation of budget estimates and various evaluation reports.


    The epoxy resin project completed the park feasibility study expert review and project filing in June , and the environmental impact assessment, safety assessment, and job evaluation contracts were signed; in July , it obtained the investment approval of Yangnong Group, completed the project design and process package opening; it is currently underway Preliminary design and preparation of budget estimates and various evaluation reports.


    A B phase of the project a B stage of the project

    Construction stage: engineering design and bidding and procurement

    Construction stage: engineering design and bidding and procurement

    At present, the ion-exchange membrane project is proceeding in an orderly manner as planned.


    At present, the ion-exchange membrane project is proceeding in an orderly manner as planned.


    Due to the supporting requirements of the ECH project and the phenol acetone project, this project has made corresponding adjustments, made two design changes, added some equipment, and completed the recruitment and recapitalization work.


    Carbon triple industry a project -carbon triple industry a project

    Construction stage: preliminary design and budget estimate review

    Construction stage: preliminary design and budget estimate review

    In June , the general plan of the public and auxiliary engineering and phenol acetone plant of the carbon three phase I project passed the review.


    In June , the general plan of the public and auxiliary engineering and phenol acetone plant of the carbon three phase I project passed the review.


    Ruitai Company Nylon 66 and Intermediate Project Ruitai Company Nylon 66 and Intermediate Project

    Construction stage: preliminary design and budget estimate review

    Construction stage: preliminary design and budget estimate review

    The core technology of nylon 66 and intermediate J project is independently researched and developed by Yangnong Group.


    The core technology of nylon 66 and intermediate J project is independently researched and developed by Yangnong Group.


    In the past two months, the project team members have continued to overcome engineering and technical difficulties despite the high temperature, and promoted the progress of the nylon project with high quality.


    Fine Chemicals and Public Auxiliary Supporting ProjectsFine Chemicals and Public Auxiliary Supporting Projects

    Construction stage: preliminary preparation

    Construction stage: preliminary preparation

    Civil construction and equipment pipeline installation, multi-heads go hand in hand

    Civil construction and equipment pipeline installation, multi-heads go hand in hand

    Ruitai Company made every effort to promote the construction of the Sinochem Zhongwei Circular Economy Industrial Park project.


    Ruitai Company made every effort to promote the construction of the Sinochem Zhongwei Circular Economy Industrial Park project.


    Central heating project is regional key projects, the project with the support of government departments, in 2019 Nian 10 months civil foundation construction, 2020 Nian 3 in late March began to return to work, 2020 Nian 7 months boiler room, chimney have been capped, 7 months 28 Ri The success of the 1# boiler water pressure test marks a new milestone for the project.


    Acetophenone Item 5 Yue 10 began the civil construction, 7 Yue 11 days, acetophenone main unit successfully completed, while speeding up the control room, power distribution room and other facilities civil construction, has entered the equipment, pipeline installation phase, The construction of the project is planned to be completed in early October .

    Under the active coordination of the company, the park and the power supply company, the 110KV substation project is progressing smoothly.
    At present, the substation workshop has been successfully capped, and preparations for electrical equipment and engineering installation are under preparation.
    The project plans to complete the project construction and grid-connected commissioning by the end of October .

    Under the active coordination of the company, the park and the power supply company, the 110KV substation project is progressing smoothly.
    At present, the substation workshop has been successfully capped, and preparations for electrical equipment and engineering installation are under preparation.
    The project plans to complete the project construction and grid-connected commissioning by the end of October .

    At the same time, under the leadership of the company’s general manager’s office, regularly organize project coordination meetings to actively promote the administrative approval, engineering design, and recruitment of demonstration projects for the recycling of hazardous waste incineration, nylon 66 and intermediates, and fine chemical by-product salt.
    Bidding work.

    At the same time, under the leadership of the company’s general manager’s office, regularly organize project coordination meetings to actively promote the administrative approval, engineering design, and recruitment of demonstration projects for the recycling of hazardous waste incineration, nylon 66 and intermediates, and fine chemical by-product salt.
    Bidding work.

    Sinochem High Fiber 5000t/ year Aramid Project of Ruisheng Company

    Ruisheng Gong Division of the High Fiber 5000t / Year aramid fiber project Ruisheng Gong Division of the High Fiber 5000t / Year aramid fiber project

    Construction stage: stand-alone debugging

    Construction stage: stand-alone debugging

    As the planned commissioning time approaches, the construction of the 5000t/ year aramid project is nearing completion.

    As the planned commissioning time approaches, the construction of the 5000t/ year aramid project is nearing completion.

    At present, all the civil engineering units of the project have been checked and accepted, and the finishing work of building decoration, site leveling, road and pipe network laying is underway.
    The installation of equipment and pipelines in each workshop is basically in place, and pipeline pressure testing, leak testing, cleaning and single-machine debugging of equipment are successively carried out.
    The installation of key imported equipment is in place, waiting for foreign technical experts to arrive at the site for adjustment, guidance, and acceptance confirmation.

    At present, all the civil engineering units of the project have been checked and accepted, and the finishing work of building decoration, site leveling, road and pipe network laying is underway.
    The installation of equipment and pipelines in each workshop is basically in place, and pipeline pressure testing, leak testing, cleaning and single-machine debugging of equipment are successively carried out.
    The installation of key imported equipment is in place, waiting for foreign technical experts to arrive at the site for adjustment, guidance, and acceptance confirmation.

    All production departments intervene in the project's installation and production preparations in advance, track and investigate the installation quality, put forward rectification suggestions for installations that are not conducive to actual production operations, conduct PHA node analysis, check flow charts, organize the compilation of operating procedures and sort out the production procedures Equipment establishment ledger, etc.

    All production departments intervene in the project's installation and production preparations in advance, track and investigate the installation quality, put forward rectification suggestions for installations that are not conducive to actual production operations, conduct PHA node analysis, check flow charts, organize the compilation of operating procedures and sort out the production procedures Equipment establishment ledger, etc.

    The project team closely cooperates to strictly control the entire construction process from the aspects of safety, quality and schedule.
    The closer it is to the end, the more management and control must be strengthened to ensure the steady progress of project construction and a perfect ending.

    The project team closely cooperates to strictly control the entire construction process from the aspects of safety, quality and schedule.
    The closer it is to the end, the more management and control must be strengthened to ensure the steady progress of project construction and a perfect ending.

    Rui Zhaoke Company Electronic Chemical Project

    Rui Zhaoke Electronic Chemicals Project Rui Zhaoke Electronic Chemicals Project

    Construction stage: civil construction

    Construction stage: civil construction

    As of the end of August , the 15700 tons / year electronic chemicals HP project of Jiangsu Ruizhaoke Electronic Materials Co.
    , Ltd.
    has carried out secondary masonry work for all buildings, indoor and outdoor wall plastering and paint construction, and related water, electricity, fire protection, Mechanical and electrical construction such as heating and ventilation; the main concrete pouring of the fire pump house of the fire pool is completed, and the closed water test and waterproof construction work are ready to be carried out.
    The main structure construction of the outdoor pipe gallery is carried out step by step and sub-regions; the steel structure is installed on site.

    As of the end of August , the 15700 tons / year electronic chemicals HP project of Jiangsu Ruizhaoke Electronic Materials Co.
    , Ltd.
    has carried out secondary masonry work for all buildings, indoor and outdoor wall plastering and paint construction, and related water, electricity, fire protection, Mechanical and electrical construction such as heating and ventilation; the main concrete pouring of the fire pump house of the fire pool is completed, and the closed water test and waterproof construction work are ready to be carried out.
    The main structure construction of the outdoor pipe gallery is carried out step by step and sub-regions; the steel structure is installed on site.

    Ruizhaoke’s electronic chemicals project puts summer safety construction in the first place of all work, further clarifies the leadership responsibility system, establishes a summer safety production leadership group, strengthens the organization and leadership of construction work, and highlights the importance of taking care to prevent heatstroke, cooling, and fire prevention.
    Summer safety construction management work focusing on explosion prevention, food poisoning prevention, and prevention of electric shock.

    Ruizhaoke’s electronic chemicals project puts summer safety construction in the first place of all work, further clarifies the leadership responsibility system, establishes a summer safety production leadership group, strengthens the organization and leadership of construction work, and highlights the importance of taking care to prevent heatstroke, cooling, and fire prevention.
    Summer safety construction management work focusing on explosion prevention, food poisoning prevention, and prevention of electric shock.

    Under the premise of doing a good job in summer heatstroke prevention and control, the epidemic prevention and control is not relaxed, people and goods are separated, the admission process and the epidemic prevention and control measures at the construction site are standardized, and the construction personnel enter the site to disinfect.

    Under the premise of doing a good job in summer heatstroke prevention and control, the epidemic prevention and control is not relaxed, people and goods are separated, the admission process and the epidemic prevention and control measures at the construction site are standardized, and the construction personnel enter the site to disinfect.

    Ruixiang company equipment optimization transformation project

    Ruixiang device optimized reconstruction project means to optimize Ruixiang company reconstruction project

    Construction stage: project approval, feasibility study preparation

    Construction stage: project approval, feasibility study preparation

    After the renovation of public works

    After the renovation of public works

    Before public works renovation

    Before public works renovation

    The ultimate goal of Ruixiang’s equipment optimization and transformation project is to improve the intrinsic safety of the equipment, and the Class A design institute is invited to carry out the intrinsic safety diagnosis of each equipment.
    Based on the organization of process calibration and device optimization, the company has implemented automation transformation and upgrading, and has successfully completed the transformation of public works with 7 ℃ water and put it into operation to meet the company's core product cold demand.

    The ultimate goal of Ruixiang’s equipment optimization and transformation project is to improve the intrinsic safety of the equipment, and the Class A design institute is invited to carry out the intrinsic safety diagnosis of each equipment.
    Based on the organization of process calibration and device optimization, the company has implemented automation transformation and upgrading, and has successfully completed the transformation of public works with 7 ℃ water and put it into operation to meet the company's core product cold demand.

    In response to the mandatory deadlines in the "Basic Requirements for Intrinsic Safety Diagnosis and Governance" and "Three-year Action Plan for National Work Safety Special Remediation" and other documents, we vigorously promoted the implementation of the "Safety Remediation Improvement Project" and "Intrinsic Safety Diagnosis Improvement Project" on the J2 plot.
    At present, the two project plans and project approval have been completed, and the project feasibility study preparation work is in progress.
    The next step will be the project investment approval work.
    The implementation of this project involves the survival of the company and is in line with the company's safety development strategy, and safety benefits will surely be further brought into play.

    In response to the mandatory deadlines in the "Basic Requirements for Intrinsic Safety Diagnosis and Governance" and "Three-year Action Plan for National Work Safety Special Remediation" and other documents, we vigorously promoted the implementation of the "Safety Remediation Improvement Project" and "Intrinsic Safety Diagnosis Improvement Project" on the J2 plot.
    At present, the two project plans and project approval have been completed, and the project feasibility study preparation work is in progress.
    The next step will be the project investment approval work.
    The implementation of this project involves the survival of the company and is in line with the company's safety development strategy, and safety benefits will surely be further brought into play.

    The cadres and employees who have devoted themselves to the construction of Yangnong's transformation and upgrading project are seizing the opportunity and working hard to accelerate the industrial layout of "one center, three bases" and the construction of integrated bases.
    The 5,000- ton / year aramid plant at Yizheng Base and the acetophenone and auxiliary equipment at Ningxia Zhongwei Base will be completed and commissioned in the fourth quarter of this year; Lianyungang Base Aromatic Phase I, Phase B , C3 and Reinforcement Project, Ningxia Zhongwei Base Projects such as 66 and its key intermediates strive to be completed and commissioned by 2021 in advance .
    The advancement and completion of a series of key projects will surely lay a more solid foundation for the company's profit growth next year.

    The cadres and employees who have devoted themselves to the construction of Yangnong's transformation and upgrading project are seizing the opportunity and working hard to accelerate the industrial layout of "one center, three bases" and the construction of integrated bases.
    The 5,000- ton / year aramid plant at Yizheng Base and the acetophenone and auxiliary equipment at Ningxia Zhongwei Base will be completed and commissioned in the fourth quarter of this year; Lianyungang Base Aromatic Phase I, Phase B , C3 and Reinforcement Project, Ningxia Zhongwei Base Projects such as 66 and its key intermediates strive to be completed and commissioned by 2021 in advance .
    The advancement and completion of a series of key projects will surely lay a more solid foundation for the company's profit growth next year.
    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.