Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
On October 19, the second phase of the caprolactam expansion project of Xuyang Group Cangzhou Park with an annual output of 300,000 tons was officially raised to full capacity and successfully reached production
.
The second phase of the Cangzhou Park of Xuyang Group with an annual output of 300,000 tons of caprolactam expansion project was put into operation from 11:38 on September 25, to 14:34 on October 18, the reflow liquid of the oxide-chemical plant was raised to the design full load, the crystallizer feed of the ammonium sulfate plant matched the oxime load at 14:36 on October 18, and then the caprolactam finished product was fully produced at 14:37 on October 19, which lasted 24 days
.
The successful production of the second phase of the plant marks that the 300,000-ton-per-year caprolactam expansion project of Xuyang Group's Cangzhou Park, which has lasted more than two years, has entered a stable operation stage, and with the first phase of 150,000 tons/year caprolactam production capacity, Xuyang Group's Cangzhou Park has become an important coastal polyamide industrial base
with an annual production capacity of 450,000 tons/year.
Combined with the 300,000 tons/year caprolactam production capacity of Xuyang Group Dongming Park, the overall scale of Xuyang caprolactam reached 750,000 tons/year, stepping into the forefront
of the country.