    With a total investment of 750 million, Xiangyun shares accelerate the construction of phosphogypsum utilization projects

    • Last Update: 2021-07-30
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    "It is necessary to focus on the progress of environmental protection and ensure that the comprehensive utilization of phosphogypsum is completed ahead of schedule, so as to contribute to the protection of the ecological environment of the Yangtze River
    .
    " Hu Huawen, chairman of Hubei Xiangyun (Group) Chemical Co.


    , Ltd.


    It is understood that Xiangyun actively responds to national policies and strictly adheres to the environmental bottom line of solid waste utilization and safe disposal.
    It started the comprehensive utilization of phosphogypsum in early June, with a total investment of 750 million yuan, which will be constructed in two phases and is expected to be completed by the end of May 2023
    .
    After the project is completed, it will play a good demonstration effect in the industry and achieve a win-win situation for both ecological and economic benefits


    .


    According to reports, the project comprehensively utilizes 6 million tons of phosphogypsum annually, basically realizing the balance of production and use of Xiangyun Company's phosphogypsum, ensuring the company's sustainable development
    .
    At the same time, it is estimated that the annual new operating income will be 558.


    64 million yuan, the annual new net profit will be 163.


    Since the start of the project for more than a month, Xiangyun's construction team has strengthened the spirit of responsibility, refined and quantified the promotion process and node tasks of project construction, reversed the construction period, and assigned responsibilities to individuals, achieving clear goals, clear tasks, and clear responsibilities
    .
    The construction team fought the high temperature, braved the scorching heat, and worked overtime day and night, forming a good atmosphere and strong synergy for project construction


    .


    As of now, the power distribution station of the project has been completed 15 days ahead of schedule, and the main factory building and warehouse are under construction at an over-speed to ensure early completion and early production


    Aerial view of the project

    Aerial view of the project
    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.