    Recently, the construction project of the ±1100kV UHV transformer base of Baobian Electric Qinchange Company was successfully completed according to the plan, and other acceptance work such as plant completion acceptance and fire protection is actively advancing, and it is expected to be put into operation
    before mid-to-late January.

    The project lasted for more than a year, experienced the construction of rainy season and cold winter, overcame a series of difficulties such as short construction period and difficulty, implemented according to the project schedule, strictly grasped safety management, quality management, progress and investment management, steadily promoted the project construction, and finally successfully completed the implementation of this project, which was highly praised
    by the leaders of the military uniform group and the construction department of the local government.

    After completion, the new plant is spacious and bright, with beautiful environment, and adopts first-class production and processing equipment at home and abroad, which meets the standard of
    domestic first-class transformer workshop.
    ± completion of the 1100kV UHV transformer base construction project on schedule, it will further improve the production capacity and technical level of UHV transformer of Baobian Electric, and improve the production and process equipment level
    of UHV transformer products.
    It is of great significance to improve the ability of
    independent innovation.

    Recently, the construction project of the ±1100kV UHV transformer base of Baobian Electric Qinchange Company was successfully completed according to the plan, and other acceptance work such as plant completion acceptance and fire protection is actively advancing, and it is expected to be put into operation
    before mid-to-late January.

    UHV

    The project lasted for more than a year, experienced the construction of rainy season and cold winter, overcame a series of difficulties such as short construction period and difficulty, implemented according to the project schedule, strictly grasped safety management, quality management, progress and investment management, steadily promoted the project construction, and finally successfully completed the implementation of this project, which was highly praised
    by the leaders of the military uniform group and the construction department of the local government.

    After completion, the new plant is spacious and bright, with beautiful environment, and adopts first-class production and processing equipment at home and abroad, which meets the standard of
    domestic first-class transformer workshop.
    ± completion of the 1100kV UHV transformer base construction project on schedule, it will further improve the production capacity and technical level of UHV transformer of Baobian Electric, and improve the production and process equipment level
    of UHV transformer products.
    It is of great significance to improve the ability of
    independent innovation.

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.