Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
Sinopec News Network reported on the evening of July 14, the last trestle bridge of the Zhenhai Base Coal and Coke Storage and Transportation Project undertaken by the Fifth Engineering Branch of Nanjing Engineering Company was safely and steadily in place.
The main structure of the coal and coke storage and transportation system was fully integrated, and the construction of the project was achieved.
Phased victory
.
The project’s trestle has a total length of 120 meters and a total weight of more than 600 tons
.
In order to ensure the safety of hoisting, the project department overcomes difficulties in the arrival of prefabricated raw materials, restricted site space, and weather in the rainy season.
From the completion of the first hoisting column hoisting on June 8th to the final truss hoisting of the last span on the evening of July 14th, the prefabrication of the steel structure of the 600-ton trestle bridge and 12 large-scale hoisting works were successfully completed within 37 days
.
In order to ensure the progress of the project, all 12 hoisting works were carried out at night.
After the main structure of the coal coke storage and transportation system is completed, the project department will start the belt threading and welding, the receiving circuit line opening, and the equipment debugging to ensure that various tasks are carried out according to the node
(Liu Jinjin and Li Shu)