Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
Sinopec News Network reported on June 3 that the relocation project of the Huangqiao Gas Field Mining and Processing Plant of East China Petroleum Bureau designed by Nanjing Engineering Company passed the 30% model review
.
The project will build a set of 350,000 tons/year industrial premium grade carbon dioxide purification and liquefaction equipment, relocate 100,000 tons/year and 200,000 tons/year industrial grade purification and liquefaction equipment, supporting carbon dioxide storage and loading, condensate storage, Exhaust gas incinerator and public works and auxiliary facilities
In the early stage of the project, software maintenance personnel continue to explore the establishment of an effective three-dimensional design platform, and gradually improve the standard database system, coordinate various professional design data under the three-dimensional model, develop company-level standard databases and set templates, accumulate practical application experience, and explore the design collaboration process The intelligent interactive application method of China Data improves the efficiency of project design
.
All professional designers and software engineers remotely cooperate to complete 3D modeling work with high quality before 30% model review
At the meeting, participants conducted in-depth exchanges and discussions on the completeness, accuracy, and rationality of the equipment layout.
The pipeline profession combined with the three-dimensional model, and actively communicated with the owner, technical experts, etc.
, from the perspectives of safety, technology, operation and maintenance.
Modify and perfect the device layout and pipeline layout to ensure the accuracy and rationality of the design work
.
The review team conducted a special review on the constructability, construction cost, construction plan and other aspects of the used equipment, and created sufficient conditions for advancing the detailed design progress of the project
After review, the 30% model review of the project was successfully completed, which was highly recognized by the owner, and fully prepared for the comprehensive development of the detailed design
(Li Shudang Yaru)