    The pressure test of Zhejiang Petrochemical's residual oil hydrogenation pipeline enters the sprint stage

    • Last Update: 2021-08-07
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    Sinopec News.
    com.
    In the past few days, two sets of 3 million tons/year slurry bed residual oil hydrogenation unit process pipeline pressure test of Zhejiang Petrochemical Phase II project undertaken by the Tenth Construction Company of Refining and Chemical Engineering have entered the sprint stage, in order to realize the start-up of the unit on schedule The feed target creates favorable conditions
    .

    It is understood that the two 3 million tons/year slurry-bed residue hydrogenation units are the core component of the second phase of Zhejiang Petrochemical Project and one of the key lines for the construction of the second phase of Zhejiang Petrochemical Company by Ten Construction Company
    .


    The total installed process pipelines of the two slurry-bed residual oil hydrogenation units are 730,000 inches in diameter and 1,770 pipeline pressure test packages.


    Since the completion of the main body of the process pipeline installation, the second phase of the Zhejiang Petrochemical Project Department of Ten Construction quickly established a pipeline pressure test team, prepared the pipeline pressure test plan in advance, communicated and coordinated closely with the owner, supervision, design and other units, and promoted by accelerating the completion of pipeline construction.


    In the pipeline pressure test, the project department implements grid management, and the persons in charge of each unit of the two sets of residual oil hydrogenation units pay close attention to the pipeline pressure test operation site, and actively implement the materials, water sources, temporary electricity, etc.


    As of July 20, the project department has completed 1,590 process pipeline pressure test packages, accounting for nearly 90% of the total.


    (Tian Yuanwu)

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.