    The main substation of the Bluestar Adisseo project successfully received power once

    • Last Update: 2021-08-08
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    Sinopec News Network reported on July 14 that the main substation of Bluestar Adisseo Nanjing Phase II 180,000 tons/year liquid methionine project undertaken by Nanjing Engineering Company was successfully supplied with electricity at one time, creating good conditions for the subsequent process development
    .

    The project is an expansion project, which will build a 180,000 tons/year liquid methionine production line.
    After completion, the whole plant will have 2 production lines, and the production capacity will be expanded from 170,000 tons/year to 350,000 tons/year
    .


    At 2:56 pm, the N030 main substation power receiving work officially began


    In response to the construction task of this substation, the project department actively planned and organized carefully, sorted out the workload in detail, formulated a practical construction plan, and rationally used other professional work gaps to arrange construction
    .


    In the early stage of power reception, a special power reception working group was established to repeatedly refine the delivery process, formulate a detailed and rigorous power reception plan in accordance with the commissioning requirements, clarify responsibilities, implement the division of labor, and actively strengthen communication with the owner, management, and supervisor , Closely docking, to ensure that the power receiving process is fully controlled, and the power receiving work is successfully completed


    In the next step, the project department will continue to optimize the allocation of resources, refine the construction plan, and launch a sprint towards the mechanical completion of the project on October 30


    (Chen Yan Li Shu)

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.