    The main equipment installation of Zhejiang high-pressure polyethylene project is completed

    • Last Update: 2021-08-07
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    Sinopec News Network reported on July 16, the high-pressure polyethylene plant extrusion pelletizer equipment of the Zhejiang Petrochemical Phase II project undertaken by the Tenth Construction Company of Refining and Chemical Engineering was successfully installed in place, marking the completion of the main completion target of the equipment installation of the project
    .

    It is understood that the high-pressure polyethylene device is an important part of the second phase of the Zhejiang Petrochemical Project and one of the key lines of the Ten Construction Company in the construction of the project
    .


    The high-pressure polyethylene device includes 320 moving equipment and 427 static equipment, with a relatively tight construction period and narrow construction operations


    The project department of the second phase of the ten construction Zhejiang Petrochemical Company closely focused on the overall construction node target requirements of the high-pressure polyethylene device formulated by the owner unit, closely followed the professional drawings of the equipment and the status of the materials in place, and organized the equipment installation and construction labor competition in a timely manner according to the on-site construction operating conditions
    .


    Thanks to the hard work of the staff participating in the construction, the installation progress of the high-pressure polyethylene device equipment has advanced by leaps and bounds, giving the entire project a good momentum of construction


    In the equipment installation, the project department carried out scientific planning for cranes, trucks and other large-scale machinery and equipment, optimized and perfected the equipment installation plan, and implemented the equipment modularization strategy to reduce the hidden dangers of equipment installation in high-altitude operations, lifting and hoisting and other safety risks
    .


    According to statistics, the project department relies on the advantages of modular installation of equipment, reducing various hidden risks by nearly 60% compared with the traditional equipment installation mode, and improving the construction efficiency by 2 times.


    At present, with the smooth completion of equipment installation, high-pressure polyethylene process piping, electrical instrumentation, anti-corrosion insulation and other construction professions have entered the final sprint stage, and the safety, quality, and progress of the entire project construction are always under control


    (Tian Yuanwu)

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.