echemi logo
Product
  • Product
  • Supplier
  • Inquiry
    Home > Chemicals Industry > International Chemical > The fourth Denmark-Norway interconnection line was approved for reserved capacity until the end of 2019

    The fourth Denmark-Norway interconnection line was approved for reserved capacity until the end of 2019

    • Last Update: 2022-12-28
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    The Danish Energy Appeals Board has ruled that Norse National Grid and Danish National Grid are likely to continue to reserve capacity for resource swaps on an interconnection between the two countries until the end of
    2019.

    The fourth Denmark-Norway interconnection line was approved for reserved capacity until the end of 2019

    "This is good news and meets the prerequisites
    for building interconnected lines.
    Previous rulings by the Danish Energy Regulatory Authority did not allow reserved capacity, and we are pleased that the current ruling allows us to maintain agreements
    between transmission operators.
    Øivind Rue, executive vice president of Norwegian National Grid, said
    .

    Since the commissioning of the fourth interconnection line (SK4) between Norway and Denmark, 100 MW of the total capacity of 1700 MW has been reserved for automatic standby
    .
    These spare capacities are important
    to maintain the operation of the power system in the event of faults and rapid changes in power flows.

    The Danish Energy Regulatory Authority approved the capacity reservation before the commissioning of the interconnection line and said it would evaluate it after a year before deciding to stop the reservation
    .
    Transmission operators referred the decision to the Complaints Board, which has now ruled that capacity
    can be retained until the end of the agreement at the end of 2019.

    The reservation of reserve capacity is an important prerequisite
    for Norslander's investment in the fourth interconnection line between the two countries.
    The Danish National Grid estimates the added value of such capacity reservations in Denmark and Norway to be at least DKK 60 million
    .


    The Danish Energy Appeals Board has ruled that Norse National Grid and Danish National Grid are likely to continue to reserve capacity for resource swaps on an interconnection between the two countries until the end of
    2019.

    Interconnects

    The fourth Denmark-Norway interconnection line was approved for reserved capacity until the end of 2019

    The fourth Denmark-Norway interconnection line was approved for reserved capacity until the end of 2019

    "This is good news and meets the prerequisites
    for building interconnected lines.
    Previous rulings by the Danish Energy Regulatory Authority did not allow reserved capacity, and we are pleased that the current ruling allows us to maintain agreements
    between transmission operators.
    Øivind Rue, executive vice president of Norwegian National Grid, said
    .

    Since the commissioning of the fourth interconnection line (SK4) between Norway and Denmark, 100 MW of the total capacity of 1700 MW has been reserved for automatic standby
    .
    These spare capacities are important
    to maintain the operation of the power system in the event of faults and rapid changes in power flows.

    The Danish Energy Regulatory Authority approved the capacity reservation before the commissioning of the interconnection line and said it would evaluate it after a year before deciding to stop the reservation
    .
    Transmission operators referred the decision to the Complaints Board, which has now ruled that capacity
    can be retained until the end of the agreement at the end of 2019.

    The reservation of reserve capacity is an important prerequisite
    for Norslander's investment in the fourth interconnection line between the two countries.
    The Danish National Grid estimates the added value of such capacity reservations in Denmark and Norway to be at least DKK 60 million
    .

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.