Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
Recently, the Tianjin Petrochemical Propylene Oxide Plant R201B reactor, which was undertaken by the Fourth Construction Company, was hoisted in place at one time, completing the first hoisting task
.
The secondary oxidation reactor R201B in the epoxidation reaction zone of the device weighs 61 tons and is completed by a 450-ton crane and a 180-ton crane
.
The biggest difficulty of this hoisting is that the site is narrow, civil construction is being carried out simultaneously, and cross operations are faced
During the hoisting process, all types of work closely cooperated and operated in accordance with the prior technical clarification procedures to successfully complete the first hoisting task, which was highly praised by the owner, general contractor, and supervisor
(Fu Qiang Liu Hailong)