    Sinopec News Network News on the evening of October 7th, the first equipment of the Hainan Refining & Chemical Ethylene C8 combined plant contracted by Nanjing Engineering Company EPC was hoisted in place as a whole for the five-tower decarbonization, which opened the prelude to the installation of large-scale equipment for the project, marking the project Fully entered a new stage of equipment installation and construction
    .

    It is understood that the C8 combined plant will build a new 550,000-ton/year pyrolysis gasoline hydrogenation unit and a 350,000-ton/year aromatic extraction unit, with a total of 11 large towers
    .


    The five decarbonization towers that have been hoisted are 3.


    The project department carried out meticulous planning and careful planning and arrangement from the early stage drawing design, tower plate procurement, feedback of tower internals, delivery of manufacturing drawings, and later large-scale transportation to ensure that the equipment arrives on-site on time
    .


    After arriving, the project department carried out in-depth prefabrication, assembling, debugging and acceptance on a module basis, realizing the in-depth linkage and cooperation between disciplines


    In order to reduce high-altitude operations and safety risks, and improve work efficiency, the project department organizes personnel to complete labor protection, pipe support installation, tower anti-corrosion and heat preservation work on the ground in accordance with modular construction planning and combined with the specific conditions of the site.
    The electrical instrument professional closely cooperates , Work overtime to complete electrical lighting installation, cable laying, wiring test photos, preliminary basic acceptance and processing work
    .

    At 19:00 of the same day, under the command of the lifting personnel, the equipment was smoothly placed on the basis
    .


    As the temporary power supply is switched on, the tower body lighting lamp emits a dazzling light, achieving the set goal of "wearing clothes and hats and lighting the tower"


    (Zhang Jinfu and Li Shu)

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Related Articles

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.