Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
China Petrochemical News Network reported on April 12 that the Hainan Refining & Chemical Corporation's 1 million tons/year ethylene plant foundation constructed by the Fourth Construction Company successfully completed the concrete pouring operation of the C407 base cap of the propylene distillation tower.
According to reports, the propylene distillation tower C407 of the device is 110 meters high, the foundation floor is a rectangular raft foundation, the cap is 2.
During the construction process, the project department of the Fourth Construction Company made scientific arrangements and overall overall planning.
In view of the large number of construction foundation bolts, large amount of steel bars, and construction in rainy seasons, the project department organized construction technicians to review drawings in advance, and continuously optimized the construction plan according to the actual situation on the site, and compiled two special projects for deep foundation pit and mass concrete pouring.
Before concrete pouring, the project department made detailed safety technical clarifications to the operators, strictly implemented various safety and quality grid control measures, reviewed key links such as temperature measurement, cooling and maintenance measures, and strengthened the process control of each process.
(Qu Zhaogui Zhongkai)